Construction Update - 6/27/2025
PLEASE consistently check your front door daily for time sensitive notifications.
Project Area
- See the construction phasing map here.
Phase 1
- Vehicles cannot be parked on the street during construction.
- Roadway excavation on Van Buren Ave is scheduled to begin Monday, 6/30.
- Sump line installation on Van Buren Ave is complete.
- Roadway excavation on Jackson Ave in preparation for curb and gutter is complete.
- Check your front door daily for notification of temporary driveway access or water loss.
Alleys west of Madison Avenue
- Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is scheduled for the week of 6/30.
- Alley paving will occur at a future date when the roadways are paved.
Phase 2
- Temporary water line installation is complete.
- Watermain replacement on Monroe Ave has been rescheduled to begin on 7/2 due to weather delays.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.