Construction Update - 6/6/2025
PLEASE consistently check your front door daily for time sensitive notifications.
Project Area
- See the construction phasing map here.
Phase 1
- Vehicles cannot be parked on the street during construction.
- Storm sewer installation will begin the week of 6/9.
- Water service installation on Jackson Ave is complete.
- Watermain service installation begins on Van Buren Ave the week of 6/9.
- Check your front door daily for notification of temporary driveway access or water loss.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the roadways are paved.
Phase 2
- Curb and gutter removal is complete.
- Temporary water line installation begins the week of 6/9.
CenterPoint Energy
- CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
- For additional information regarding the Maloney Avenue road closure can be found here.
- All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.
Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.