Construction Update - 7/11/2025
Project Area
- The neighborhood phasing map has changed for the second consecutive week. See the UPDATED construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Concrete curb and gutter installation is complete. Driveways will be accessible by the end of the day on Wednesday, 7/16.
- The first layer of asphalt paving is scheduled for Thursday, 7/17, weather permitting.
- Asphalt driveways will be replaced at a later date.
Alleys west of Madison Avenue
- Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is complete.
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Watermain replacement is complete on Monroe and Madison Aves.
- Water service installation will begin the week of 7/14.
Phase 3
- Removals of the existing curb and driveway ends on Adams Ave and Washington Ave are scheduled to begin on Monday, 7/14.
Share Construction Update - 7/11/2025 on Facebook