Construction Update - 7/11/2025

Project Area

  • The neighborhood phasing map has changed for the second consecutive week. See the UPDATED construction phasing map.


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Concrete curb and gutter installation is complete. Driveways will be accessible by the end of the day on Wednesday, 7/16.
  • The first layer of asphalt paving is scheduled for Thursday, 7/17, weather permitting.
  • Asphalt driveways will be replaced at a later date.


Alleys west of Madison Avenue

  • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is complete.
  • Alley paving will occur at a future date when the Phase 2 roadways are paved.


Phase 2

  • Watermain replacement is complete on Monroe and Madison Aves.
  • Water service installation will begin the week of 7/14.


Phase 3

  • Removals of the existing curb and driveway ends on Adams Ave and Washington Ave are scheduled to begin on Monday, 7/14.