Construction Update - 7/18/2025
Project Area
- See the UPDATED construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- The first layer of asphalt paving is complete.
- Asphalt driveways are scheduled for paving the week of 7/21.
- Excavation in preparation for topsoil installation will begin the week of 7/21.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Watermain replacement is complete on Monroe and Madison Aves.
- Water service installation will continue the week of 7/21.
Phase 3
- Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/21.