Construction Update - 7/2/2026
Project Area
- No work will occur on Friday, July 3rd in observance of Independence Day holiday.
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until early July. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Sod installation, irrigation repairs and replacement of impacted landscaping will continue into the week of 7/6.
- Paving the final layer of asphalt is tentatively scheduled for the week of 7/6.
- Sign installation is scheduled to occur the week of 7/6.
- Check your front door daily for notifications.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Any outstanding sod issues are scheduled to occur the week of 7/6.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Share Construction Update - 7/2/2026 on Facebook
Share Construction Update - 7/2/2026 on X (formerly Twitter)
Share Construction Update - 7/2/2026 on Linkedin
Email Construction Update - 7/2/2026 link