Construction Update – 7/25/2025

Project Area


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Asphalt driveways are complete.
  • Excavation in preparation for topsoil installation will begin the week of 7/28.
  • Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.


Alleys west of Madison Avenue

  • A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
  • Alley paving will occur at a future date when the Phase 2 roadways are paved.


Phase 2

  • Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
  • Water service installation on Madison Ave is complete.


Phase 3

  • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
  • Temporary water lines are scheduled to be setup the week of 7/28.