Construction Update – 7/25/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Asphalt driveways are complete.
- Excavation in preparation for topsoil installation will begin the week of 7/28.
- Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.
Alleys west of Madison Avenue
- A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
- Water service installation on Madison Ave is complete.
Phase 3
- Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
- Temporary water lines are scheduled to be setup the week of 7/28.