Construction Update – 7/3/2025

No work will occur on Friday, 7/4. Have a safe and happy Happy 4th of July!
Project Area
- The neighborhood phasing map has CHANGED. See the UPDATED construction phasing map.
Phase 1
- Vehicles cannot be parked on the street during construction.
- Roadway excavation on Van Buren Ave is complete.
- Concrete curb and gutter installation is scheduled to begin on Tuesday, 7/8 weather permitting.
- Check your front door daily for notification of temporary driveway access or water loss.
Alleys west of Madison Avenue
- Storm sewer replacement in the alley between Madison Ave and Jefferson Ave has been rescheduled for the week of 7/7.
- Alley paving will occur at a future date when the roadways are paved.
Phase 2
- Temporary water line installation is complete.
- Watermain replacement on Monroe Ave will continue into the week of 7/7.
- Watermain replacement on Madison Ave is scheduled to begin the week of 7/7.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 3
- Reclaiming the road pavement is scheduled for 7/9. Reclaiming is the process of grinding the existing asphalt into a gravel base.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Share Construction Update – 7/3/2025 on Facebook
Share Construction Update – 7/3/2025 on Twitter
Share Construction Update – 7/3/2025 on Linkedin
Email Construction Update – 7/3/2025 link
