Construction Update – 8/1/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Concrete path installation along Belmore Lane is complete.
- Excavation in preparation for topsoil installation will continue the week of 8/4.
- Retaining wall installation is scheduled to begin the week of 8/4.
Alleys west of Madison Avenue
- The concrete valley gutter and curb installation is complete.
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Water service installations are complete on Monroe and Madison Ave.
- Storm sewer and sump line installation will continue the week of 8/4.
Phase 3
- Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
- Temporary water line installation is scheduled to continue into the week of 8/4.