Construction Update – 8/1/2025

Project Area


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Concrete path installation along Belmore Lane is complete.
  • Excavation in preparation for topsoil installation will continue the week of 8/4.
  • Retaining wall installation is scheduled to begin the week of 8/4.


Alleys west of Madison Avenue

  • The concrete valley gutter and curb installation is complete.
  • Alley paving will occur at a future date when the Phase 2 roadways are paved.


Phase 2

  • Water service installations are complete on Monroe and Madison Ave.
  • Storm sewer and sump line installation will continue the week of 8/4.


Phase 3

  • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
  • Temporary water line installation is scheduled to continue into the week of 8/4.



Share Construction Update – 8/1/2025 on Facebook Share Construction Update – 8/1/2025 on Twitter Share Construction Update – 8/1/2025 on Linkedin Email Construction Update – 8/1/2025 link