Construction Update – 8/15/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Excavation in preparation for topsoil installation is complete.
- Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
- Landscaping replacement will continue the week of 8/18.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
- Sump line installation is complete.
- Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Temporary water line installation is scheduled to continue into the week of 8/18.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Anticipate short term water loss during this process.
- Installation of the new water main is scheduled to begin the week of 8/18.
Share Construction Update – 8/15/2025 on Facebook
Share Construction Update – 8/15/2025 on Twitter
Share Construction Update – 8/15/2025 on Linkedin
Email Construction Update – 8/15/2025 link
