Construction Update – 8/15/2025

Project Area


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Excavation in preparation for topsoil installation is complete.
  • Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
  • Landscaping replacement will continue the week of 8/18.


Alleys west of Madison Avenue

  • Alley paving will occur at a future date when the Phase 2 roadways are paved.


Phase 2

  • Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
  • Sump line installation is complete.
  • Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).


Phase 3

  • Curb and driveway apron removals are complete.
  • Temporary water line installation is scheduled to continue into the week of 8/18.
    • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Anticipate short term water loss during this process.
  • Installation of the new water main is scheduled to begin the week of 8/18.