Construction Update – 8/22/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 8/25.
- Sod installation is complete.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Excavation of poor soils in preparation for the new roadway will continue into the week of 8/25.
- To avoid extended driveway access closures around the Labor Day holiday, curb and gutter installation is tentatively rescheduled to begin the week of 9/2 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Temporary water line installation is scheduled to continue into the week of 8/25.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Anticipate short term water loss during this process.
- Installation of the new water main on Washington Ave is complete.
- Watermain installation on Jefferson Ave is scheduled to begin the week of 8/25
Share Construction Update – 8/22/2025 on Facebook
Share Construction Update – 8/22/2025 on Twitter
Share Construction Update – 8/22/2025 on Linkedin
Email Construction Update – 8/22/2025 link
