Construction Update - 8/29/25
Construction Update – 8/29/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 9/2.
- Sod installation is complete.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Concrete curb and gutter installation are scheduled to begin on Tuesday, 9/2 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Installation of new water services on Washington Ave is complete.
- Watermain installation on Jefferson Ave is complete.
- Water service installation on Jefferson Ave is scheduled for the week of 9/2.
- Watermain lining on Maloney Ave is scheduled to begin the week of 9/8.
Phase 5
- Temporary water is being setup on Tyler Ct in preparation for watermain lining that is scheduled to begin the week of 9/8.