Construction Update – 8/8/2025

Project Area

All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Excavation in preparation for topsoil installation will continue the week of 8/11.
  • Retaining wall installation is complete.
  • Replacement of landscape items that were removed during construction will begin the week of 8/11.


Alleys west of Madison Avenue

  • Alley paving will occur at a future date when the Phase 2 roadways are paved.


Phase 2

  • Storm sewer installation is complete.
  • Sump line installation will continue the week of 8/11.
  • Removal and replacement of poor soils in preparation for the new roadway is scheduled to begin the week of 8/11.


Phase 3

  • Removals of the existing curb and driveway ends on Adams Ave, and Belmore Ave will continue into the week of 8/11.
  • Temporary water line installation is scheduled to continue into the week of 8/11.
    • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Anticipate short term water loss during this process.
  • Installation of the new water main is scheduled to begin the week of 8/11.