Construction Update – 8/8/2025
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Excavation in preparation for topsoil installation will continue the week of 8/11.
- Retaining wall installation is complete.
- Replacement of landscape items that were removed during construction will begin the week of 8/11.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Storm sewer installation is complete.
- Sump line installation will continue the week of 8/11.
- Removal and replacement of poor soils in preparation for the new roadway is scheduled to begin the week of 8/11.
Phase 3
- Removals of the existing curb and driveway ends on Adams Ave, and Belmore Ave will continue into the week of 8/11.
- Temporary water line installation is scheduled to continue into the week of 8/11.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Anticipate short term water loss during this process.
- Installation of the new water main is scheduled to begin the week of 8/11.
Share Construction Update – 8/8/2025 on Facebook
Share Construction Update – 8/8/2025 on Twitter
Share Construction Update – 8/8/2025 on Linkedin
Email Construction Update – 8/8/2025 link
