Construction Update – 9/12/2025

Maloney Avenue Road Closure

  • Please see the road closure update here for details.


Project Area

  • See the construction phasing map.


All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Landscaping replacement will continue the week of 9/15.
  • Sod care
    • See written and video sod care tips here and here.
    • To prevent sod damage, please avoid walking on or mowing it initially.
    • The contractor will be watering for the first 60 days.
    • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
  • The final layer of asphalt paving is scheduled for late October.


Phase 2

  • The first layer of asphalt paving is scheduled for Monday, 9/15. Please have all vehicles off the street by 7am.
  • Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/15.


Phase 3

  • Water service installation on Jefferson Ave is complete.
  • Sump line installation will continue into the week of 9/15.
  • Watermain lining on Maloney Ave will continue into the week of 9/15.


Alleys west of Madison Avenue

  • Alley paving will occur at a future date when the Phase 3 roadways are paved.


Tyler Court

  • Watermain lining on Tyler Court will continue into the week of 9/15.


Harrison and Tyler Avenues