Construction Update – 9/12/2025
Maloney Avenue Road Closure
- Please see the road closure update here for details.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 9/15.
- Sod care
- The final layer of asphalt paving is scheduled for late October.
Phase 2
- The first layer of asphalt paving is scheduled for Monday, 9/15. Please have all vehicles off the street by 7am.
- Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/15.
Phase 3
- Water service installation on Jefferson Ave is complete.
- Sump line installation will continue into the week of 9/15.
- Watermain lining on Maloney Ave will continue into the week of 9/15.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court will continue into the week of 9/15.
Harrison and Tyler Avenues