Construction Update - 9/19/2025
Road Closures
- Maloney Avenue will remain closed until Wed. 9/24.
- Washington Avenue will be CLOSED beginning Wed. 9/24 for approximately 3 weeks.
- Between Maloney Avenue and 3rd Street
- The detour route will be Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed beginning the week of 9/22. Please use other routes.
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Sod care
- The final layer of asphalt paving is scheduled for late October.
Phase 2
- The first layer of asphalt paving is complete.
- Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/22.
- Excavation in preparation for topsoil installation is scheduled to begin the week of 9/22.
- New retaining wall installation on Monroe Ave will continue into the week of 9/22.
Phase 3
- Water service installation on Adams Ave is complete.
- Sump line installation on Adams Ave will continue into the week of 9/22.
- Watermain lining on Maloney Ave will continue into the week of 9/22.
- Removal and replacement of poor soils in preparation for curb and gutter is scheduled to begin the week of 9/22.
- Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/22.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court will continue into the week of 9/22.
- The roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, and Belmore Ln