Construction Update - 9/26/2025

Road Closures


Project Area

  • See the construction phasing map.

All Phases

  • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
  • Vehicles cannot be parked on the street during construction.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Phase 1

  • Sod care
    • See written and video sod care tips here and here.
    • To prevent sod damage, please avoid walking on or mowing it initially.
    • The contractor will be watering for the first 60 days.
    • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
  • The final layer of asphalt paving is scheduled for late October.


Phase 2

  • Concrete sidewalk installation on Monroe Ave and Belmore Ln is complete.
  • Excavation in preparation for topsoil installation is scheduled to continue the week of 9/29.
  • New retaining wall installation on Monroe Ave will continue into the week of 9/29.


Phase 3

  • Crews will be onsite Saturday, 9/27 removing and replacing poor soils in preparation for curb and gutter. This work will continue the week of 9/29.
  • Sump line installation on Adams Ave is complete.
  • Watermain lining on Maloney Ave is complete.
  • Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/29.


Alleys west of Madison Avenue

  • Alley paving will occur at a future date when the Phase 3 roadways are paved.


Tyler Court

  • Watermain lining on Tyler Court is complete.
  • Brandon will be setting up times to reinstall water meters the week of 9/29 for homes affected by the watermain lining.
  • The roadway improvements have been postponed until 2026.


Harrison and Tyler Avenues and Tyler Ct