Construction Update - 5/29/2026
Project Area
- See the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
- CenterPoint Energy completed gas main and service replacements.
Phase 1:
- General Notes
- Vehicles cannot be parked on the street during construction.
- Check your front door daily for notification of temporary driveway access or water loss.
- Work will occur on Saturday, 5/30.
- Upcoming Work
- Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
- Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
- Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
- Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
- Ongoing Work
- Lanham Ln water service installation will continue into the week of 6/1.
- Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
- Completed Work
- Sump drain installation on Lee Valley Circle and Weston Circle is complete.
- Watermain installation on Lanham Lane near Kemrich Drive is complete.
Share Construction Update - 5/29/2026 on Facebook
Share Construction Update - 5/29/2026 on Twitter
Share Construction Update - 5/29/2026 on Linkedin
Email Construction Update - 5/29/2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends