Construction Update - 5/29/2026

Project Area

  • See the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.
  • CenterPoint Energy completed gas main and service replacements.


Phase 1:

  • General Notes
    • Vehicles cannot be parked on the street during construction.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Work will occur on Saturday, 5/30.
  • Upcoming Work
    • Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
      • Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
      • Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
  • Ongoing Work
    • Lanham Ln water service installation will continue into the week of 6/1.
    • Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
  • Completed Work
    • Sump drain installation on Lee Valley Circle and Weston Circle is complete.
    • Watermain installation on Lanham Lane near Kemrich Drive is complete.
Share Construction Update - 5/29/2026 on Facebook Share Construction Update - 5/29/2026 on Twitter Share Construction Update - 5/29/2026 on Linkedin Email Construction Update - 5/29/2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>