Prospect Knolls A/C/D Neighborhood Roadway Reconstruction

Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Facebook Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Twitter Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Linkedin Email Prospect Knolls A/C/D Neighborhood Roadway Reconstruction link
Map showing the Prospect Knolls neighborhood and the project limits.

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)
  • Construction Update - 6/19/2026

    Share Construction Update - 6/19/2026 on Facebook Share Construction Update - 6/19/2026 on Twitter Share Construction Update - 6/19/2026 on Linkedin Email Construction Update - 6/19/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be onsite on Saturday 6/20 preparing for pavement reclamation in Phase 1.
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane and Tara Road storm sewer and sump drain installation is scheduled to begin the week of 6/22.
      • Tara Road, Antrim Court, Antrim Terrace, and Lanham Lane reclaiming of existing asphalt is scheduled for Monday, 6/22.
      • Weston Circle, Lee Valley Circle, and Village Drive topsoil installation is scheduled to begin the week of 6/22.
    • Ongoing Work
      • Kemrich Drive, Antrim Court, Antrim Terrace, and Tara Road storm sewer installation will continue into the week of 6/22.
    • Completed Work
      • Lanham Lane, Tara Road, Antrim Court, and Antrim Terrace water service installation is complete.

    Phase 2:

    • Completed Work
      • Mail boxes have been salvaged and placed in front yards.
        • Temporary mail bank information can be found here.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be onsite on Saturday 6/20 preparing for pavement reclamation in Phase 1.
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane and Tara Road storm sewer and sump drain installation is scheduled to begin the week of 6/22.
      • Tara Road, Antrim Court, Antrim Terrace, and Lanham Lane reclaiming of existing asphalt is scheduled for Monday, 6/22.
      • Weston Circle, Lee Valley Circle, and Village Drive topsoil installation is scheduled to begin the week of 6/22.
    • Ongoing Work
      • Kemrich Drive, Antrim Court, Antrim Terrace, and Tara Road storm sewer installation will continue into the week of 6/22.
    • Completed Work
      • Lanham Lane, Tara Road, Antrim Court, and Antrim Terrace water service installation is complete.

    Phase 2:

    • Completed Work
      • Mail boxes have been salvaged and placed in front yards.
        • Temporary mail bank information can be found here.
  • Construction Update - 6/12/2026

    Share Construction Update - 6/12/2026 on Facebook Share Construction Update - 6/12/2026 on Twitter Share Construction Update - 6/12/2026 on Linkedin Email Construction Update - 6/12/2026 link

    Project Area

    • The contractor is scheduled to work on Juneteenth, Friday, June 16
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
      • Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
      • Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.

    Phase 2:

    • Upcoming Work
      • Mail boxes will be salvaged and placed in front yards on 6/19.
        • Temporary mail bank information can be found here.
      • Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.

    Project Area

    • The contractor is scheduled to work on Juneteenth, Friday, June 16
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
      • Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
      • Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.

    Phase 2:

    • Upcoming Work
      • Mail boxes will be salvaged and placed in front yards on 6/19.
        • Temporary mail bank information can be found here.
      • Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.
  • Construction Update - 6/5/2026

    Share Construction Update - 6/5/2026 on Facebook Share Construction Update - 6/5/2026 on Twitter Share Construction Update - 6/5/2026 on Linkedin Email Construction Update - 6/5/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.
    • Upcoming Work
      • Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
      • Driveways are scheduled to be temporarily restored with gravel on 6/8.
      • Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
      • Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
    • Ongoing Work
      • Lanham Lane water service installation will continue into the week of 6/8.
    • Completed Work
      • Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.
    • Upcoming Work
      • Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
      • Driveways are scheduled to be temporarily restored with gravel on 6/8.
      • Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
      • Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
    • Ongoing Work
      • Lanham Lane water service installation will continue into the week of 6/8.
    • Completed Work
      • Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.
  • Construction Update - 5/29/2026

    Share Construction Update - 5/29/2026 on Facebook Share Construction Update - 5/29/2026 on Twitter Share Construction Update - 5/29/2026 on Linkedin Email Construction Update - 5/29/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.
    • CenterPoint Energy completed gas main and service replacements.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction.
      • Check your front door daily for notification of temporary driveway access or water loss.
      • Work will occur on Saturday, 5/30.
    • Upcoming Work
      • Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
        • Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
        • Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
    • Ongoing Work
      • Lanham Ln water service installation will continue into the week of 6/1.
      • Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
    • Completed Work
      • Sump drain installation on Lee Valley Circle and Weston Circle is complete.
      • Watermain installation on Lanham Lane near Kemrich Drive is complete.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.
    • CenterPoint Energy completed gas main and service replacements.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction.
      • Check your front door daily for notification of temporary driveway access or water loss.
      • Work will occur on Saturday, 5/30.
    • Upcoming Work
      • Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
        • Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
        • Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
    • Ongoing Work
      • Lanham Ln water service installation will continue into the week of 6/1.
      • Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
    • Completed Work
      • Sump drain installation on Lee Valley Circle and Weston Circle is complete.
      • Watermain installation on Lanham Lane near Kemrich Drive is complete.
  • Construction Update - 5/22/2026

    Share Construction Update - 5/22/2026 on Facebook Share Construction Update - 5/22/2026 on Twitter Share Construction Update - 5/22/2026 on Linkedin Email Construction Update - 5/22/2026 link

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Traffic Update:

    • Expect delays on Lanham Ln southbound at Kemrich Dr on 5/27 and 5/28. Please utilize northbound Lanham Ln toward W. 70th St.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Lanham Ln watermain installation near Kemrich Drive is scheduled to begin the week of 5/26.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane and Tara Road to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Weston Circle and Lee Valley Circle sump drain installation will continue into the week of 5/26.
    • Watermain installation on Lanham Lane from W 70th Street to Fleetwood Drive is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy will continue installing new gas service lines the week of 5/26 and is expected to be complete by mid-June.
    • CenterPoint Energy will be doing some restoration work including driveway patching. All questions and concerns related to their restoration should be directed to CenterPoint Energy. They can be reached at
      • csv.restoration@centerpointenergy.com or 612-321-5477.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Traffic Update:

    • Expect delays on Lanham Ln southbound at Kemrich Dr on 5/27 and 5/28. Please utilize northbound Lanham Ln toward W. 70th St.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Lanham Ln watermain installation near Kemrich Drive is scheduled to begin the week of 5/26.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane and Tara Road to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Weston Circle and Lee Valley Circle sump drain installation will continue into the week of 5/26.
    • Watermain installation on Lanham Lane from W 70th Street to Fleetwood Drive is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy will continue installing new gas service lines the week of 5/26 and is expected to be complete by mid-June.
    • CenterPoint Energy will be doing some restoration work including driveway patching. All questions and concerns related to their restoration should be directed to CenterPoint Energy. They can be reached at
      • csv.restoration@centerpointenergy.com or 612-321-5477.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.
  • Construction Update - 5/15/2026

    Share Construction Update - 5/15/2026 on Facebook Share Construction Update - 5/15/2026 on Twitter Share Construction Update - 5/15/2026 on Linkedin Email Construction Update - 5/15/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • All roads are scheduled to be reclaimed on 5/18. Reclaiming is the process of grinding the existing asphalt into a gravel base.
      • Lanham Ln will be partially reclaimed. The remainder will be reclaimed as the work progresses to reduce erosion.
    • Lanham Ln new watermain installation will begin the week of 5/18.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Antrim Ct, Antrim Terr, and Tara Rd temporary watermain set up will continue into the week of 5/18.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Hydrant, watermain gate valve, and water service replacement on Lee Valley Circle and Weston Circle are complete.


    Xcel Energy:

    • Xcel Energy began removing streetlights on Lanham Lane, Tara Road, Kemrich Drive, Weston Circle, and Village Drive to prepare for their upcoming streetlight replacement project.


    CenterPoint Energy:

    • CenterPoint Energy will start installing new gas service lines the week of 5/18 and is expected to be complete by mid-June.
    • CenterPoint Energy has completed gas main installation.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • All roads are scheduled to be reclaimed on 5/18. Reclaiming is the process of grinding the existing asphalt into a gravel base.
      • Lanham Ln will be partially reclaimed. The remainder will be reclaimed as the work progresses to reduce erosion.
    • Lanham Ln new watermain installation will begin the week of 5/18.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Antrim Ct, Antrim Terr, and Tara Rd temporary watermain set up will continue into the week of 5/18.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Hydrant, watermain gate valve, and water service replacement on Lee Valley Circle and Weston Circle are complete.


    Xcel Energy:

    • Xcel Energy began removing streetlights on Lanham Lane, Tara Road, Kemrich Drive, Weston Circle, and Village Drive to prepare for their upcoming streetlight replacement project.


    CenterPoint Energy:

    • CenterPoint Energy will start installing new gas service lines the week of 5/18 and is expected to be complete by mid-June.
    • CenterPoint Energy has completed gas main installation.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.
  • Construction Update - 5/8/2026

    Share Construction Update - 5/8/2026 on Facebook Share Construction Update - 5/8/2026 on Twitter Share Construction Update - 5/8/2026 on Linkedin Email Construction Update - 5/8/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Weston Circle water service replacements are scheduled to begin the week of 5/11.
    • Lee Valley Circle hydrant and watermain gate valve replacements are scheduled for the week of 5/11.
    • Lanham Lane water service replacements are scheduled to begin later during the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Water service replacement on Lee Valley Circle and Village Drive is complete.


    CenterPoint Energy:

    • CenterPoint Energy continues replacing old gas pipes in a portion of the project area this spring and is expected to conclude by mid-June.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Weston Circle water service replacements are scheduled to begin the week of 5/11.
    • Lee Valley Circle hydrant and watermain gate valve replacements are scheduled for the week of 5/11.
    • Lanham Lane water service replacements are scheduled to begin later during the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Water service replacement on Lee Valley Circle and Village Drive is complete.


    CenterPoint Energy:

    • CenterPoint Energy continues replacing old gas pipes in a portion of the project area this spring and is expected to conclude by mid-June.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


  • Construction Update - 5/1/2026

    Share Construction Update - 5/1/2026 on Facebook Share Construction Update - 5/1/2026 on Twitter Share Construction Update - 5/1/2026 on Linkedin Email Construction Update - 5/1/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • A select number of trees will be removed throughout the project area during the week of 5/4 due to the roadway and utility improvements. These trees have been marked with ribbon or paint.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Temporary mail bank installation is complete.
    • Standard mail boxes have been salvaged for reinstallation at the conclusion of the project. Larger mail boxes will be removed later.
    • Water service replacement is scheduled to begin on Lee Valley Circle the week of 5/4.
    • Construction vehicles, equipment, and materials is scheduled to be brought to site the week of 5/4.
    • Set up of temporary watermain on Lanham Ln, Tara Rd, Antrim Ct, and Antrim Ter will begin in preparation of watermain improvements the week of 5/4. Temporary watermain locations are shown in the map here.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy began replacing old gas pipes in a portion of the project area this spring.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • A select number of trees will be removed throughout the project area during the week of 5/4 due to the roadway and utility improvements. These trees have been marked with ribbon or paint.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Temporary mail bank installation is complete.
    • Standard mail boxes have been salvaged for reinstallation at the conclusion of the project. Larger mail boxes will be removed later.
    • Water service replacement is scheduled to begin on Lee Valley Circle the week of 5/4.
    • Construction vehicles, equipment, and materials is scheduled to be brought to site the week of 5/4.
    • Set up of temporary watermain on Lanham Ln, Tara Rd, Antrim Ct, and Antrim Ter will begin in preparation of watermain improvements the week of 5/4. Temporary watermain locations are shown in the map here.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy began replacing old gas pipes in a portion of the project area this spring.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


  • Construction Kickoff!

    Share Construction Kickoff! on Facebook Share Construction Kickoff! on Twitter Share Construction Kickoff! on Linkedin Email Construction Kickoff! link

    As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.


    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • A select number of trees will be removed throughout the project area due to the roadway and utility improvements. These trees have been marked with ribbon or paint.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Construction vehicles, equipment, and materials is scheduled to be brought to site the week of 4/27.
    • Set up of temporary watermain will begin in preparation of watermain improvements the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy began replacing old gas pipes in a portion of the project area this spring.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is notpart of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


    As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.


    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • A select number of trees will be removed throughout the project area due to the roadway and utility improvements. These trees have been marked with ribbon or paint.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Construction vehicles, equipment, and materials is scheduled to be brought to site the week of 4/27.
    • Set up of temporary watermain will begin in preparation of watermain improvements the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy began replacing old gas pipes in a portion of the project area this spring.
    • CenterPoint Energy will also be replacing gas meters inside of property owners homes, relocating them outside.
    • CenterPoint Energy's work is notpart of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


  • Temporary Mail Bank Locations - Phase 1

    Share Temporary Mail Bank Locations - Phase 1 on Facebook Share Temporary Mail Bank Locations - Phase 1 on Twitter Share Temporary Mail Bank Locations - Phase 1 on Linkedin Email Temporary Mail Bank Locations - Phase 1 link

    We apologize for the confusion regarding the notifications given out for the temporary mail bank locations. These were prepared by a subcontractor, with errors, and delivered without the City's approval. Mail delivery at these temporary mail banks is scheduled to begin on Wednesday, April 29. The temporary mail bank information for the following Phase 1 streets can be found here.

    Again, we're sorry for the confusion.



    We apologize for the confusion regarding the notifications given out for the temporary mail bank locations. These were prepared by a subcontractor, with errors, and delivered without the City's approval. Mail delivery at these temporary mail banks is scheduled to begin on Wednesday, April 29. The temporary mail bank information for the following Phase 1 streets can be found here.

    Again, we're sorry for the confusion.



Page last updated: 18 Jun 2026, 03:35 PM