Construction Update - 6/12/2026

Project Area

  • The contractor is scheduled to work on Juneteenth, Friday, June 16
  • See the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.


Phase 1 & 2:

  • General Notes
    • Vehicles cannot be parked on the street during construction working hours.
    • Check your front door daily for notification of temporary driveway access or water loss.

Phase 1

  • Upcoming Work
    • The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
    • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
    • Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
    • Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
  • Ongoing Work
    • Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.

Phase 2:

  • Upcoming Work
    • Mail boxes will be salvaged and placed in front yards on 6/19.
      • Temporary mail bank information can be found here.
    • Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
    • Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
    • Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.