Construction Update - 6/12/2026
Project Area
- The contractor is scheduled to work on Juneteenth, Friday, June 16
- See the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 1
- Upcoming Work
- The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
- Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
- Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
- Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
- Ongoing Work
- Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.
Phase 2:
- Upcoming Work
- Mail boxes will be salvaged and placed in front yards on 6/19.
- Temporary mail bank information can be found here.
- Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
- Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
- Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.
- Mail boxes will be salvaged and placed in front yards on 6/19.
Share Construction Update - 6/12/2026 on Facebook
Share Construction Update - 6/12/2026 on Twitter
Share Construction Update - 6/12/2026 on Linkedin
Email Construction Update - 6/12/2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends