Phase 1 & 2:

  • General Notes
    • Crews may be onsite on Saturday 6/20 preparing for pavement reclamation in Phase 1.
    • Vehicles cannot be parked on the street during construction working hours.
    • Check your front door daily for notification of temporary driveway access or water loss.

Phase 1

  • Upcoming Work
    • Lanham Lane and Tara Road storm sewer and sump drain installation is scheduled to begin the week of 6/22.
    • Tara Road, Antrim Court, Antrim Terrace, and Lanham Lane reclaiming of existing asphalt is scheduled for Monday, 6/22.
    • Weston Circle, Lee Valley Circle, and Village Drive topsoil installation is scheduled to begin the week of 6/22.
  • Ongoing Work
    • Kemrich Drive, Antrim Court, Antrim Terrace, and Tara Road storm sewer installation will continue into the week of 6/22.
  • Completed Work
    • Lanham Lane, Tara Road, Antrim Court, and Antrim Terrace water service installation is complete.

Phase 2:

  • Completed Work
    • Mail boxes have been salvaged and placed in front yards.
      • Temporary mail bank information can be found here.