Construction Update - 6/26/2026
Project Area
- See the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Crews may be on site Saturday 6/27 installing topsoil on Weston Circle, Lee Valley Circle, and Village Drive
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 1
- Upcoming Work
- Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is scheduled to begin the week of 6/29.
- Lee Valley Circle, Weston Circle, and Village Drive mailbox installation is scheduled to begin late during the week of 6/29.
- Mail delivery to your permanent mailbox should resume soon after it's installed.
- Ongoing Work
- Lee Valley Circle, Weston Circle, and Village Drive topsoil installation will continue into the week of 6/29.
- Completed Work
- Lanham Lane, Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is complete.
Phase 2:
- Upcoming Work
- Dublin Road and Wexford Road watermain installation is scheduled to begin the week of 6/29.
- Fleetwood Drive water service replacement is scheduled to begin the week of 6/29.
Share Construction Update - 6/26/2026 on Facebook
Share Construction Update - 6/26/2026 on X (formerly Twitter)
Share Construction Update - 6/26/2026 on Linkedin
Email Construction Update - 6/26/2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends