Construction Update - 6/26/2026

Project Area

  • See the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.


Phase 1 & 2:

  • General Notes
    • Crews may be on site Saturday 6/27 installing topsoil on Weston Circle, Lee Valley Circle, and Village Drive
    • Vehicles cannot be parked on the street during construction working hours.
    • Check your front door daily for notification of temporary driveway access or water loss.

Phase 1

  • Upcoming Work
    • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is scheduled to begin the week of 6/29.
    • Lee Valley Circle, Weston Circle, and Village Drive mailbox installation is scheduled to begin late during the week of 6/29.
      • Mail delivery to your permanent mailbox should resume soon after it's installed.
  • Ongoing Work
    • Lee Valley Circle, Weston Circle, and Village Drive topsoil installation will continue into the week of 6/29.
  • Completed Work
    • Lanham Lane, Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is complete.

Phase 2:

  • Upcoming Work
    • Dublin Road and Wexford Road watermain installation is scheduled to begin the week of 6/29.
    • Fleetwood Drive water service replacement is scheduled to begin the week of 6/29.
Share Construction Update - 6/26/2026 on Facebook Share Construction Update - 6/26/2026 on X (formerly Twitter) Share Construction Update - 6/26/2026 on Linkedin Email Construction Update - 6/26/2026 link