Construction Update - 6/5/2026
Project Area
- See the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary driveway access or water loss.
- Upcoming Work
- Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
- Driveways are scheduled to be temporarily restored with gravel on 6/8.
- Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
- Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
- Ongoing Work
- Lanham Lane water service installation will continue into the week of 6/8.
- Completed Work
- Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.
Share Construction Update - 6/5/2026 on Facebook
Share Construction Update - 6/5/2026 on Twitter
Share Construction Update - 6/5/2026 on Linkedin
Email Construction Update - 6/5/2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends