Construction Update - 6/5/2026

Project Area

  • See the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.


Phase 1:

  • General Notes
    • Vehicles cannot be parked on the street during construction working hours.
    • Check your front door daily for notification of temporary driveway access or water loss.
  • Upcoming Work
    • Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
    • Driveways are scheduled to be temporarily restored with gravel on 6/8.
    • Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
    • Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
  • Ongoing Work
    • Lanham Lane water service installation will continue into the week of 6/8.
  • Completed Work
    • Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.