Construction Update - 7/2/2026
Gleason Road Closure Notice
Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements beginning on Wednesday, 7/8 until approximately Wednesday, 7/22. The detour route will be Hilary Lane and Valley View Road.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- No work will occur on Friday, July 3rd in observance of Independence Day holiday.
- Please see the REVISED construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary driveway access or water loss.
Phase 1
- Upcoming Work
- Sod installation will begin when weather permits
- Ongoing Work
- Lanham Lane, Kemrich Drive, and Tara Road sump drain installation will continue into the week of 7/6.
- Completed Work
- Mailbox reinstallation on Lee Valley Circle and Weston Circle.
Phase 2:
- Upcoming Work
- Fleetwood Drive hydrant and gate valve installation is scheduled to begin the week of 7/6.
- Fleetwood Drive storm sewer installation is scheduled to begin the week of 7/6.
- Ongoing Work
- Salvaging of remaining mailboxes will continue the week of 7/6. Mailboxes will be placed in front yards
- Dublin Road and Wexford Road watermain installation will continue the week of 7/6.
- Completed Work
- Fleetwood Drive water service installation is complete.
Share Construction Update - 7/2/2026 on Facebook
Share Construction Update - 7/2/2026 on X (formerly Twitter)
Share Construction Update - 7/2/2026 on Linkedin
Email Construction Update - 7/2/2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends