April 22, 2026 Update

Council reviewed the bids and construction schedules for the project at last nights City Council Meeting. They instructed staff to bring back a contract with a June 1, 2027 completion. This would save $1.1 million compared to a December 1, 2026 completion date. They also want to partially clad the project in the architectural panels. The partial cladding includes the bridge and transitions to railings along the access ramps. A contract will be awarded after we have a signed cooperative agreement from MnDOT. Thanks