January 22, 2025 Project Update

The project team shared a project update with the City Council on January 21, 2025. The presentation slides can be found in the document area. The video of the discussion can be found here. https://edinamn.portal.civicclerk.com/ The team has been working on lots of details related to the steel truss bridge, landings, ramps, architectural panels, and user experience. The unique nature of the bridge requires us to hire a bridge fabricator to advance the 30% plans to bidding documents with less risk. There are two major items affecting project budget – potential stairs and the camber of the steel truss bridge. Once a bridge fabricator is added to the team, cost estimates will be more actual to determine what can be included in the project.