Rosland Park Pedestrian Bridge Replacement
The Rosland Park Pedestrian Bridge is a piece of critical transportation infrastructure that must be replaced. The bridge connects the north and south communities by providing a safe overpass bridge above Minnesota Highway 62. It is a critical connection for pedestrians from northern Edina to safely access Rosland Park and its amenities, including the Edina Aquatic Center.
The current pedestrian bridge is owned and managed by the Minnesota Department of Transportation (MnDOT). It was built in the 1960s. The bridge does not meet Americans with Disabilities Act (ADA) standards and was substantially damaged when it was struck twice in 2022 by vehicles traveling on Minnesota Highway 62. The damage resulted in the closure of the bridge for most of 2022, until expensive temporary repairs were made in January 2023.
Project goals
- Improve safety and mobility for all users
- Create ADA compliant pedestrian and bike route
- Improve connectivity between the residential neighborhoods and Rosland Park
- Limit impacts on residential and park properties, trees, and road operations with an eye on long term operations and maintenance

The Rosland Park Pedestrian Bridge is a piece of critical transportation infrastructure that must be replaced. The bridge connects the north and south communities by providing a safe overpass bridge above Minnesota Highway 62. It is a critical connection for pedestrians from northern Edina to safely access Rosland Park and its amenities, including the Edina Aquatic Center.
The current pedestrian bridge is owned and managed by the Minnesota Department of Transportation (MnDOT). It was built in the 1960s. The bridge does not meet Americans with Disabilities Act (ADA) standards and was substantially damaged when it was struck twice in 2022 by vehicles traveling on Minnesota Highway 62. The damage resulted in the closure of the bridge for most of 2022, until expensive temporary repairs were made in January 2023.
Project goals
- Improve safety and mobility for all users
- Create ADA compliant pedestrian and bike route
- Improve connectivity between the residential neighborhoods and Rosland Park
- Limit impacts on residential and park properties, trees, and road operations with an eye on long term operations and maintenance

-
March 13, 2026 Update Tree Removals
Share March 13, 2026 Update Tree Removals on Facebook Share March 13, 2026 Update Tree Removals on Twitter Share March 13, 2026 Update Tree Removals on Linkedin Email March 13, 2026 Update Tree Removals linkThe tree removals are scheduled Monday, March 23. Only trees in public City or MnDOT right-of-way will be removed. We are not removing any trees on private property. Tree clearing is recommended from November 1 to March 31 to protect endangered bat species, specifically the northern long-eared bat. This window also helps prevent the spread of diseases like oak wilt and protects nesting birds. The contractor will place plywood to protect the street near the trees. They will access the site from Valley View Road and St. Johns Avenue. Thanks
-
March 4, 2026 Update
Share March 4, 2026 Update on Facebook Share March 4, 2026 Update on Twitter Share March 4, 2026 Update on Linkedin Email March 4, 2026 Update linkThere was some confusion on a recent project update. The update stated council would consider a tree removal contract on March 3. At the time, we did not know if the contract value would be above or below $20,000. Council is required to approve all contracts above $20k. In this case, the low bid came in at $13,500. That does not require council approval. Staff can approve that contract. I apologize for not updating the website last week when this become known. The contract has been approved. Only trees in public City or MnDOT right-of-way will be removed. We are not removing any trees on private property. Tree clearing is recommended from November 1 to March 31 to protect endangered bat species, specifically the northern long-eared bat. This window also helps prevent the spread of diseases like oak wilt and protects nesting birds. Tree removals are scheduled to occur before March 31. Thanks
-
February 13, 2026 Tree Removal Update
Share February 13, 2026 Tree Removal Update on Facebook Share February 13, 2026 Tree Removal Update on Twitter Share February 13, 2026 Tree Removal Update on Linkedin Email February 13, 2026 Tree Removal Update link
Staff has requested quotes from tree contractors to remove 0.20 acres of trees within the project area on the north side of Highway 62 by March 31. Access for this work is from 64th Street. The contractor is required to submit a street protection plan to be approved prior to work occurring. Any disturbed areas are required to be stabilized with hydro-seed and mulch. Any fence removal to gain access to the work area from 64th Street will be re-installed. Quotes are due February 23. City Council will consider award of the contract on March 3. Thanks, Chad Millner.
-
February 9, 2026 Update
Share February 9, 2026 Update on Facebook Share February 9, 2026 Update on Twitter Share February 9, 2026 Update on Linkedin Email February 9, 2026 Update linkWe are in the final steps of official MnDOT approval of the project. The project will go out for bids in late February or March. Alternate bids will be collected. Cladding is one of the alternate bids. Construction is planned for 2026 with or without the cladding based on discussions with the Council related to bids and budgets. Tree clearing along the north side of Highway 62 will occur before the end of March.
-
January 8, 2026 Noise Wall Update
Share January 8, 2026 Noise Wall Update on Facebook Share January 8, 2026 Noise Wall Update on Twitter Share January 8, 2026 Noise Wall Update on Linkedin Email January 8, 2026 Noise Wall Update linkOn December 4, 2025, MnDOT held a noise wall community meeting related to noise walls near the Rosland Park Pedestrian Bridge. These noise walls are related to the westbound Hwy 62 auxiliary lane and shoulder widening project. They are located along the north side of Hwy 62 from approximately West 62nd St. to Valley View Rd and along the south side of Hwy 62 from approximately West 64th St. to West Shore Dr. Project details can be found here. https://www.dot.state.mn.us/metro/projects/hwy62edina/ Specific properties had an opportunity to vote for or against noise walls. The results are in. Both walls will be constructed based on the voting results. Voting results can be found here. https://www.dot.state.mn.us/metro/projects/hwy62edina/nbi.html.
-
Sept. 18, 2025 Update
Share Sept. 18, 2025 Update on Facebook Share Sept. 18, 2025 Update on Twitter Share Sept. 18, 2025 Update on Linkedin Email Sept. 18, 2025 Update link
At the September 16, 2025 City Council Meeting, staff provided the council with a project update. Many discussions have been occurring with MnDOT on approvals of the new bridge. Update cost estimates were completed and there are concerns with the estimated cost compared to the $6M overall project budget. All the slides from the presentation are posted in the documents section of the website.
Options
$6M BUDGET – ALL STATE FUNDS
Estimated Construction Cost with 10% Contingency
Estimated Construction Cost Combinations with 10% Contingency ($515,000)
Total Project Costs with Indirect Costs ($1,500,000)
1. Base Bid – No Cladding and No Stairs
$5,660,000
$7,160,000
2. Base plus Bridge Only Cladding
$275,000
$5,935,000 (1+2)
$7,435,000
3. Base plus Ramp Cladding
$345,000
$6,280,000 (1+2+3)
$7,780,000
4. Stairs North
$300,000
$5,960,000 (1+4)
$6,380,000 (1+4+5)
$7,460,000
$7,880,000
5. Stairs South
$420,000
$6,080,000 (1+5)
$6,380,000 (1+4+5)
$7,580,000
$7,880,000
-
June 5, 2025 Update
Share June 5, 2025 Update on Facebook Share June 5, 2025 Update on Twitter Share June 5, 2025 Update on Linkedin Email June 5, 2025 Update linkDesign of the Rosland Park Pedestrian Bridge continues. A great team of structural engineers, architects and a bridge fabricator are working on the project to ensure we are the most efficient with our time and better understand construction costs. The project is at a design milestone. It is approximately 30% designed. This means we can submit the 30% plans to MnDOT to start the discussion of requirements over Highway 62. This will be a unique discussion because of the decorative architecture panels. The estimated project cost was updated. Recall the project has a $6 million budget, all state funds. Construction costs and unknowns are increasing and affecting the budget. The project will mostly likely not be able to afford stairs features or be able to bury the overhead power lines. The cost estimate will be revisited after our discussions with MnDOT. Thanks, Chad Millner, City Engineer.
-
April 7, 2025 Project Update
Share April 7, 2025 Project Update on Facebook Share April 7, 2025 Project Update on Twitter Share April 7, 2025 Project Update on Linkedin Email April 7, 2025 Project Update linkA bridge fabricator has been hired and added to the team. Discussions continue on lots of details related to the steel truss bridge, landings, ramps, architectural panels, and user experience. The unique nature of the bridge requires us to figure out those details before engaging MnDOT on the bridge design. There are two major items affecting project budget – potential stairs and the camber of the steel truss bridge. Now that we have a bridge fabricator on the team, cost estimates will be more actual to determine what can be included in the project.
-
January 22, 2025 Project Update
Share January 22, 2025 Project Update on Facebook Share January 22, 2025 Project Update on Twitter Share January 22, 2025 Project Update on Linkedin Email January 22, 2025 Project Update link
The project team shared a project update with the City Council on January 21, 2025. The presentation slides can be found in the document area. The video of the discussion can be found here. https://edinamn.portal.civicclerk.com/ The team has been working on lots of details related to the steel truss bridge, landings, ramps, architectural panels, and user experience. The unique nature of the bridge requires us to hire a bridge fabricator to advance the 30% plans to bidding documents with less risk. There are two major items affecting project budget – potential stairs and the camber of the steel truss bridge. Once a bridge fabricator is added to the team, cost estimates will be more actual to determine what can be included in the project.
-
August 1, 2024 Project Update
Share August 1, 2024 Project Update on Facebook Share August 1, 2024 Project Update on Twitter Share August 1, 2024 Project Update on Linkedin Email August 1, 2024 Project Update linkBolton Menk has finished the concept level work to study possible bridge concepts and determine what will fit best. They have also started working with the preferred architect, Snow Kreilich. Both firms need an opportunity to work on specific details related to the concept and structural engineering. They are looking at whether or not stairs could be added. They have also developed a project schedule. The new bridge will require an approval by the state bridge engineer and that takes time. Construction will most likely occurr in 2026. As updates occur, staff will be updating the BetterTogetherEdina website and City Council as appropriate.
Public Participation Level

Who's Listening
-
Phone 952-826-0318 Email cmillner@EdinaMN.gov
Key Dates
-
December 14 2023
-
December 19 2023
-
January → March 2024
-
April → September 2024
-
October 2024 → January 2025
Documents
-
20250916 Rosland Ped Bridge Council Meeting.pdf (1.05 MB) (pdf)
-
20250603 Rosland Ped Bridge Council Meeting.pdf (1.04 MB) (pdf)
-
20250121 Rosland Ped Bridge Council Meeting.pdf (2.25 MB) (pdf)
-
Values Viewfinder Memo - Rosland Park Ped Bridge Staff Workshop.pdf (304 KB) (pdf)
-
TH 62 Bridge Concept Set Feb 2024.pdf (8.92 MB) (pdf)
-
Rosland Ped Bridge Concept Matrix Summary_Feb 2024.pdf (129 KB) (pdf)
-
Auxiliary Lane and Noise Wall Graphic_Dec 2023 (4.95 MB) (pdf)
-
Matrix and Concepts_Dec 2023.pdf (2.28 MB) (pdf)
-
Edina Pedestrian Bridge_03-01-24.pdf (75.4 MB) (pdf)
-
2024 03 04_Updated North Views wo Wall.pdf (80.9 MB) (pdf)
-
20240312 Rosland Bridge Staff Report compressed.pdf (23.8 MB) (pdf)
-
BKV Proposal (11.1 MB) (pdf)
-
BKV Rendering Image #1 (6.84 MB) (jpg)
-
BKV Rendering Image #2 (5.93 MB) (jpg)
-
BKV Rendering Image #3 (1.08 MB) (jpg)
-
NEXT Proposal (16.3 MB) (pdf)
-
NEXT Rendering Image #1 (6.52 MB) (jpg)
-
NEXT Rendering Image #2 (7.39 MB) (jpg)
-
NEXT Rendering Image #3 (6.28 MB) (jpg)
-
Snow Kreilich Proposal (10.2 MB) (pdf)
-
Snow Kreilich Rendering Image #1 (1.33 MB) (jpg)
-
Snow Kreilich Rendering Image #2 (2.52 MB) (jpg)
-
Snow Kreilich Rendering Image #3 (1.83 MB) (jpg)