South Trunk Sanitary Sewer

Share South Trunk Sanitary Sewer on Facebook Share South Trunk Sanitary Sewer on Twitter Share South Trunk Sanitary Sewer on Linkedin Email South Trunk Sanitary Sewer link

The City of Edina has initiated the South Trunk Sanitary Sewer Improvements project in your area to renew and enhance infrastructure, ensure long-term service reliability, and better prepare for redevelopment. Over the next few months, the City of Edina will listen to and keep the public informed, acknowledge concerns, and address any impact to the public. We will work to ensure considerations are reflected in the option we develop and provide feedback on how public input influenced the final project design plans.

Planning and design ends in December 2025. Construction is estimated to be phased between 2026 and 2030.


The City of Edina has initiated the South Trunk Sanitary Sewer Improvements project in your area to renew and enhance infrastructure, ensure long-term service reliability, and better prepare for redevelopment. Over the next few months, the City of Edina will listen to and keep the public informed, acknowledge concerns, and address any impact to the public. We will work to ensure considerations are reflected in the option we develop and provide feedback on how public input influenced the final project design plans.

Planning and design ends in December 2025. Construction is estimated to be phased between 2026 and 2030.


  • Open House 2 Virtual Option

    Share Open House 2 Virtual Option on Facebook Share Open House 2 Virtual Option on Twitter Share Open House 2 Virtual Option on Linkedin Email Open House 2 Virtual Option link

    This is a reminder to join us for Open House #2 on Monday, August 4th, 2025, from 6:00 to 8:00 p.m., with a presentation beginning at 6:10 p.m. The event will be held in the Multipurpose Room at the Edina Public Works Facility, located at 7450 Metro Blvd. If unable to join us in person, a virtual open is available:

    Microsoft Teams Need help?

    Join the meeting now

    Meeting ID: 214 120 593 146 8

    Passcode: s3ET2qs7

  • Open House 1 Virtual Option

    Share Open House 1 Virtual Option on Facebook Share Open House 1 Virtual Option on Twitter Share Open House 1 Virtual Option on Linkedin Email Open House 1 Virtual Option link
    ChatGPT said:

    This is a reminder to join us for Open House #1 (72nd Street segment) on Monday, July 28, 2025, from 6:00 to 8:00 p.m., with a presentation beginning at 6:10 p.m. The event will be held in the Multipurpose Room at the Edina Public Works Facility, located at 7450 Metro Blvd. A virtual attendance option was available and we'll be posting a recording of the meeting soon.

  • Join Us for an Open House!

    Share Join Us for an Open House! on Facebook Share Join Us for an Open House! on Twitter Share Join Us for an Open House! on Linkedin Email Join Us for an Open House! link

    The City of Edina is planning to renew and enhance the sanitary sewer infrastructure in your area to ensure long-term service reliability and better prepare for redevelopment. Join us for an open house to learn more about the project and discuss your questions.

    Open House #1 (72nd Street):

    Monday, July 28, 2025

    6 – 8 p.m., presentation at 6:10 p.m.

    Edina Public Works Facility Multipurpose Room (7450 Metro Blvd, Edina)

    Open House #2 (Oaklawn Avenue, Gilford Drive, Kellogg Avenue and Hibiscus Avenue):

    Monday, August 4, 2025

    6 – 8 p.m., presentation at 6:10 p.m.

    Edina Public Works Facility Multipurpose Room (7450 Metro Blvd, Edina)

  • Alternatives Analysis Update

    Share Alternatives Analysis Update on Facebook Share Alternatives Analysis Update on Twitter Share Alternatives Analysis Update on Linkedin Email Alternatives Analysis Update link

    The alternatives analysis is underway. The project team continues to evaluate potential construction methods for the sanitary sewer system within the project area. We anticipate public meetings will be held in either late July or early August to share alternatives and gather feedback.

  • Alternatives Analysis

    Share Alternatives Analysis on Facebook Share Alternatives Analysis on Twitter Share Alternatives Analysis on Linkedin Email Alternatives Analysis link

    The first phase of field work is now complete, including the topographic survey and initial geotechnical investigations. Over the next month, the project team will be reviewing existing site conditions and evaluating potential construction methods for the new sanitary sewer. The alternatives analysis will explore both traditional open-cut construction and trenchless installation techniques for the mainline of the sanitary sewer.

    Residents will have the opportunity to learn more about the project status and the alternative options being considered at an in-person open house this summer--stay tuned for more information. The public will have the opportunity to provide feedback on the alternatives as well as other questions or concerns they may have related to the project. Meeting materials will also be available for review on the project website.


  • Topographic Survey Starts March 17th

    Share Topographic Survey Starts March 17th on Facebook Share Topographic Survey Starts March 17th on Twitter Share Topographic Survey Starts March 17th on Linkedin Email Topographic Survey Starts March 17th link

    Beginning the week of March 17th, topographic survey will commence in the project area. You may see representatives in your neighborhood during this time.

  • We Want Your Input!

    Share We Want Your Input! on Facebook Share We Want Your Input! on Twitter Share We Want Your Input! on Linkedin Email We Want Your Input! link

    We want to hear from you! Don’t miss the chance to contribute your thoughts, ideas, and vision for the community. Keep an eye out for future engagement meeting dates.

  • Geotechnical Soil Borings and Field Survey to Begin This Month

    Share Geotechnical Soil Borings and Field Survey to Begin This Month on Facebook Share Geotechnical Soil Borings and Field Survey to Begin This Month on Twitter Share Geotechnical Soil Borings and Field Survey to Begin This Month on Linkedin Email Geotechnical Soil Borings and Field Survey to Begin This Month link

    Beginning this month, representatives from Bolton & Menk, Inc. and Braun Intertec will initiate field investigations of soil and survey conditions to help us plan. You may see them in your neighborhood during this time. All work should be occurring within the public right of way.

Page last updated: 31 Jul 2025, 05:14 AM