South Trunk Sanitary Sewer
The City of Edina has initiated the South Trunk Sanitary Sewer Improvements project in your area to renew and enhance infrastructure, ensure long-term service reliability, and better prepare for redevelopment. Over the next few months, the City of Edina will listen to and keep the public informed, acknowledge concerns, and address any impact to the public. We will work to ensure considerations are reflected in the option we develop and provide feedback on how public input influenced the final project design plans.
Planning and design ends in December 2025. Construction is estimated to be phased between 2026 and 2030.
The City of Edina has initiated the South Trunk Sanitary Sewer Improvements project in your area to renew and enhance infrastructure, ensure long-term service reliability, and better prepare for redevelopment. Over the next few months, the City of Edina will listen to and keep the public informed, acknowledge concerns, and address any impact to the public. We will work to ensure considerations are reflected in the option we develop and provide feedback on how public input influenced the final project design plans.
Planning and design ends in December 2025. Construction is estimated to be phased between 2026 and 2030.
-
Open House 2 Virtual Option
Share Open House 2 Virtual Option on Facebook Share Open House 2 Virtual Option on Twitter Share Open House 2 Virtual Option on Linkedin Email Open House 2 Virtual Option linkThis is a reminder to join us for Open House #2 on Monday, August 4th, 2025, from 6:00 to 8:00 p.m., with a presentation beginning at 6:10 p.m. The event will be held in the Multipurpose Room at the Edina Public Works Facility, located at 7450 Metro Blvd. If unable to join us in person, a virtual open is available:
Microsoft Teams Need help?
Meeting ID: 214 120 593 146 8
Passcode: s3ET2qs7
-
Open House 1 Virtual Option
Share Open House 1 Virtual Option on Facebook Share Open House 1 Virtual Option on Twitter Share Open House 1 Virtual Option on Linkedin Email Open House 1 Virtual Option linkChatGPT said:
This is a reminder to join us for Open House #1 (72nd Street segment) on Monday, July 28, 2025, from 6:00 to 8:00 p.m., with a presentation beginning at 6:10 p.m. The event will be held in the Multipurpose Room at the Edina Public Works Facility, located at 7450 Metro Blvd. A virtual attendance option was available and we'll be posting a recording of the meeting soon.
-
Join Us for an Open House!
Share Join Us for an Open House! on Facebook Share Join Us for an Open House! on Twitter Share Join Us for an Open House! on Linkedin Email Join Us for an Open House! linkThe City of Edina is planning to renew and enhance the sanitary sewer infrastructure in your area to ensure long-term service reliability and better prepare for redevelopment. Join us for an open house to learn more about the project and discuss your questions.
Open House #1 (72nd Street):
Monday, July 28, 2025
6 – 8 p.m., presentation at 6:10 p.m.
Edina Public Works Facility Multipurpose Room (7450 Metro Blvd, Edina)
Open House #2 (Oaklawn Avenue, Gilford Drive, Kellogg Avenue and Hibiscus Avenue):
Monday, August 4, 2025
6 – 8 p.m., presentation at 6:10 p.m.
Edina Public Works Facility Multipurpose Room (7450 Metro Blvd, Edina)
-
Alternatives Analysis Update
Share Alternatives Analysis Update on Facebook Share Alternatives Analysis Update on Twitter Share Alternatives Analysis Update on Linkedin Email Alternatives Analysis Update linkThe alternatives analysis is underway. The project team continues to evaluate potential construction methods for the sanitary sewer system within the project area. We anticipate public meetings will be held in either late July or early August to share alternatives and gather feedback.
-
Alternatives Analysis
Share Alternatives Analysis on Facebook Share Alternatives Analysis on Twitter Share Alternatives Analysis on Linkedin Email Alternatives Analysis linkThe first phase of field work is now complete, including the topographic survey and initial geotechnical investigations. Over the next month, the project team will be reviewing existing site conditions and evaluating potential construction methods for the new sanitary sewer. The alternatives analysis will explore both traditional open-cut construction and trenchless installation techniques for the mainline of the sanitary sewer.
Residents will have the opportunity to learn more about the project status and the alternative options being considered at an in-person open house this summer--stay tuned for more information. The public will have the opportunity to provide feedback on the alternatives as well as other questions or concerns they may have related to the project. Meeting materials will also be available for review on the project website.
-
Topographic Survey Starts March 17th
Share Topographic Survey Starts March 17th on Facebook Share Topographic Survey Starts March 17th on Twitter Share Topographic Survey Starts March 17th on Linkedin Email Topographic Survey Starts March 17th linkBeginning the week of March 17th, topographic survey will commence in the project area. You may see representatives in your neighborhood during this time.
-
We Want Your Input!
Share We Want Your Input! on Facebook Share We Want Your Input! on Twitter Share We Want Your Input! on Linkedin Email We Want Your Input! linkWe want to hear from you! Don’t miss the chance to contribute your thoughts, ideas, and vision for the community. Keep an eye out for future engagement meeting dates.
-
Geotechnical Soil Borings and Field Survey to Begin This Month
Share Geotechnical Soil Borings and Field Survey to Begin This Month on Facebook Share Geotechnical Soil Borings and Field Survey to Begin This Month on Twitter Share Geotechnical Soil Borings and Field Survey to Begin This Month on Linkedin Email Geotechnical Soil Borings and Field Survey to Begin This Month linkBeginning this month, representatives from Bolton & Menk, Inc. and Braun Intertec will initiate field investigations of soil and survey conditions to help us plan. You may see them in your neighborhood during this time. All work should be occurring within the public right of way.
Who's Listening
-
Phone 952-903-5713 Email RBintner@EdinaMN.gov -
Phone 612-756-3427 Email sarah.lloyd@bolton-menk.com -
Phone 651-434-5743 Email haila.maze@bolton-menk.com
Tentative Project Schedule
-
February 2025 → January 2026
-
February → April 2025
-
April → June 2025
-
July 2025 → January 2026
FAQs
- What is the source of funding for this work?
- Is it possible that any property specific special assessments might fund this work?
- Is it possible that special assessments would be recommended on those parts of the project that were assessed in 2013 as part of the Lake Edina A neighborhood reconstruction?
- What was done to assess the trunk sewers condition in 2013?
- What improvements were done to the trunk sewer line in 2013?
- For part of segment 1, Why didn’t the City do this work that is contemplated now, in 2013 with the neighborhood reconstruction scope of work?
- What sort of risk controls do you use for vibration monitoring?
- Are private sewer lines at risk from the planned work?
- Who can do private sewer inspection if I want to review my sewer condition ahead of the work?
- Would the construction impact the curb and street near me?
Open House Recordings
Meeting Recordings:
Couldn’t make the July 28, 2025 meeting? Find the video on You Tube here https://youtu.be/Nfu_L5t5OLs