Southdale B Neighborhood Roadway Reconstruction

Share Southdale B Neighborhood Roadway Reconstruction on Facebook Share Southdale B Neighborhood Roadway Reconstruction on Twitter Share Southdale B Neighborhood Roadway Reconstruction on Linkedin Email Southdale B Neighborhood Roadway Reconstruction link

Southdale B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Complete replacement of the street lighting system, and
  • Construction of a concrete sidewalk along Barrie Road and a portion of West 65th Street and Heritage Drive to complete gaps in the pedestrian network.
  • A preliminary assessment amount of $950.00 per multi-family residential unit (condominium or apartment owner), was approved by the Council at the December 2023 public hearing. This $950.00 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties.

Southdale B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Complete replacement of the street lighting system, and
  • Construction of a concrete sidewalk along Barrie Road and a portion of West 65th Street and Heritage Drive to complete gaps in the pedestrian network.
  • A preliminary assessment amount of $950.00 per multi-family residential unit (condominium or apartment owner), was approved by the Council at the December 2023 public hearing. This $950.00 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties.
  • Project Update and City Council Authorization

    Share Project Update and City Council Authorization on Facebook Share Project Update and City Council Authorization on Twitter Share Project Update and City Council Authorization on Linkedin Email Project Update and City Council Authorization link

    The City Council authorized the design and contractor bidding phase for the project on December 19. Preparation of final plans and specifications will be prepared this winter, followed by solicitation of contractor bids. We anticipate construction beginning in April or May 2024. The estimated preliminary assessment amount is $950.00 per multi-family residential unit (condominium or apartment owner), payable beginning in 2025 after construction is complete.

    Following comments received during the public input period, final roadway, parking and sidewalk improvements can be viewed here.

  • Public Hearing December 11, 2023

    Share Public Hearing December 11, 2023 on Facebook Share Public Hearing December 11, 2023 on Twitter Share Public Hearing December 11, 2023 on Linkedin Email Public Hearing December 11, 2023 link

    The Engineering Study can be viewed here. To complete the public hearing comment form please click here.


    The Edina City Council will meet at Edina City Hall on Monday, Dec. 11, 2022, at 6:00 p.m., to consider the public hearing on roadway improvements for Southdale B Neighborhood Roadway Reconstruction. This hearing is being conducted under the authority granted by Minnesota Statutes, Chapter 429.


    This hearing has been called as a recommendation from staff. The proposed project would be constructed in the summer of 2024 with the assessment hearing occurring in the fall of 2025. The estimated cost is $1,095,854.05 and is funded by special assessment. The estimated cost per assessable lot is $950.00 per multi-family residential unit (condominium or apartment). The assessment can be divided over a fifteen-year period with interest accumulating on the unpaid balance.


    The City hired Nagell Appraisal Inc. to prepare a letter report providing a preliminary opinion of market benefit for similar properties in the neighborhood. The letter report is available for viewing in the document library located here.


    The area proposed to be assessed the cost of the proposed improvement includes the following:


    3330 and 3400 West 66th Street, 6300 to 6525 Barrie Road, 6301 to 6423 Colony Way, 3105 to 3456 Heritage Drive, 6200 Xerxes Avenue.

  • Proposed Roadway, Parking, and Sidewalk Locations

    Share Proposed Roadway, Parking, and Sidewalk Locations on Facebook Share Proposed Roadway, Parking, and Sidewalk Locations on Twitter Share Proposed Roadway, Parking, and Sidewalk Locations on Linkedin Email Proposed Roadway, Parking, and Sidewalk Locations link

    See the proposed roadway widths, including parking and sidewalk locations. The sidewalks are recommended per the Pedestrian Master Plan.

  • Informational Video Presentation and In Person Q & A Meeting

    Share Informational Video Presentation and In Person Q & A Meeting on Facebook Share Informational Video Presentation and In Person Q & A Meeting on Twitter Share Informational Video Presentation and In Person Q & A Meeting on Linkedin Email Informational Video Presentation and In Person Q & A Meeting link

    Please watch the informational videos about how projects are funded (special assessment, utility funds, pedestrian and cyclist safety fund and property taxes), a typical project timeline, how you will be impacted, how you can prepare, and more.

    You are also invited to review draft exhibits and ask City staff questions on Tuesday November 28 from 6 to 8 PM at the Edina Public Works Building, 7450 Metro Boulevard Edina MN 55439. No presentation will occur, as the informational videos will serve as the background details.

    We hope you find these videos informative, and we anticipate they will generate questions. Your questions can be submitted on this web page, or you can reach out to us by email or phone.


  • Soil Borings scheduled for the week of 8/7

    Share Soil Borings scheduled for the week of 8/7 on Facebook Share Soil Borings scheduled for the week of 8/7 on Twitter Share Soil Borings scheduled for the week of 8/7 on Linkedin Email Soil Borings scheduled for the week of 8/7 link

    Soil Borings are scheduled for the week of 8/7.

    This is the process of drilling holes in the ground to collect soil samples to gain a basic understanding of the subgrade conditions under the pavement. This information will assist in the roadway and utility design.


  • Welcome!

    Share Welcome! on Facebook Share Welcome! on Twitter Share Welcome! on Linkedin Email Welcome! link

    Hello and welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2024 in the Southdale B neighborhood. Important updates will be posted on this web page at various points during the Engineering Study phase. Anticipate weekly updates during construction in 2024. Key project milestones include:

    • June 2023 – Begin Engineering Study preparation
    • Fall – Informational video
    • Nov. 2023 – Engineering Study complete
    • Dec. 2023 – City Council / Public Hearing meeting to consider authorizing project design
    • Mar. 2024 – City Council meeting to consider authorizing construction
    • Apr. 2024 – Construction begins
    • Oct. 2024 – Construction substantial completion

    A series of short videos on the City's street reconstruction program can be found here.

    Feel free to call or email me with your project questions, or you can post questions on this website.

    We look forward to assisting and keeping you informed with this project.

    Aaron Ditzler