Construction Update – 11/01/2024

Although the first layer of asphalt is complete on the majority of Barrie Road and on Heritage Drive, no parking remains in effect. Please do not park on the street during working hours. You may get towed. This will give the contractor the proper space to do work. Thank you for your cooperation.


Barrie Road and Heritage Drive

  • Paving the final layer of asphalt is scheduled for 11/18.
  • The remaining sod installation is scheduled to begin the week of 11/4. See written tips for care of your new sod here and a video here.
  • Remaining sign installation is scheduled to begin the week of 11/4.
  • Retaining wall installation will continue into the week of 11/4.
  • Miscellaneous landscaping items are scheduled to begin the week of 11/4.


W. 65th Street

  • Unfortunately, Xcel Energy delays have prevented the contractor from completing both the utility work and asphalt paving on W. 65th St. Therefore, the utility and concrete curb improvements will be postponed until 2025.
  • Temporary asphalt paving is scheduled for the week of 11/18.
  • Installation of utilities and construction of the roadway and sidewalk are scheduled for Spring/Summer 2025.