Construction Update - 4/10/25
Construction on W 65th Street and Barrie Road is scheduled to resume on Monday, 4/14 and be substantially completed by 6/30. The W 65th Street work will begin with asphalt pavement removal, followed by sanitary sewer improvements.
Traffic Update
- The following roads will be CLOSED beginning on Monday, 4/14 due to sanitary sewer improvements.
- The intersection of Barrie Road and W 65th Street
- W 65th Street between Drew Avenue and Barrie Road
- Colony Way entrance from W 65thStreet
- Colony Way will be accessible from Barrie Road during this time.
- A map visualizing this traffic update can be found here.
- The intersection of Barrie Road and W 65th Street will be closed for a minimum of 2 weeks.
Metro Transit
- Metro Transit is currently constructing a new bus rapid transit station for the new E Line on W 65th Street between France Avenue and Drew Avenue in front of Southdale Hospital.
- This project is NOT part of the City’s Southdale B road reconstruction project on W 65th Street.
- The bus station construction is scheduled to be completed by the end of June 2025.
- If you have any questions or concerns about Metro Transit’s E Line project, please email ELine@metrotransit.org or call 612-524-6050.
- You can sign up to receive email updates about the E Line construction here.