Here is the weekly update for the Southdale B Neighborhood Roadway Reconstruction project:
CenterPoint Energy
- CenterPoint Energy is scheduled to begin gas main and service replacement work on 5/20.
- CenterPoint Energy’s work is expected to take 3-4 weeks.
- This work is not part of the City’s Southdale B Neighborhood Road Reconstruction contract.
- Any questions or concerns about this work, please email csv.constructionservices@centerpointenergy.com or call 612-321-5369 or 612-321-5546.
Heritage Drive and W 65th Street
- Curb and driveways removals will finish the week of 5/20.
- Temporary water setup began and will continue the week of 5/20.
- Water shut offs are necessary to switch over to temporary water and will occur the week of 5/27. You will receive notice with details during the week of 5/27.
Barrie Road
- Roadway and driveway removals will begin the week of 5/20. Vehicles may use the gravel roads and driveway entrances as you typically would.
- Please do not park on the street during working hours. You may get towed. This will give the contractor the proper space to do work. Thank you for your cooperation.