Construction Update - 5/23/2025

Traffic Update

  • W 65th Street between Drew Avenue and Barrie Road is now open to traffic.
  • There will be another W 65th Street closure in June when the final layer of asphalt paving occurs.


W. 65th Street

  • Paving the first layer of asphalt is complete.
  • Irrigation repairs and streetlight and retaining wall installations are scheduled to begin the week of 5/26. Topsoil and sod will follow after this work is complete, and the final layer of asphalt will follow the topsoil and sod work.
  • Construction is scheduled to conclude by the end of June.


Metro Transit

  • Route 578 bus service to and from Downtown Minneapolis has resumed on Barrie Road and Heritage Drive.
    • Please note that southbound buses coming from Downtown Minneapolis will NOT be servicing stops on Drew Ave and W 65th Street due to construction on W 65th Street.