Construction Update - 6/12/2025

Traffic Update

  • The following roads will remain CLOSED on Fri. 6/13 due to asphalt paving.
    • The intersection of Barrie Road and W 65th Street
      • The intersection will open on Fri. 6/13 following the rollers completing the compaction.
    • W 65th Street between Drew Avenue and Barrie Road
    • Colony Way entrance from W 65th Street
      • Colony Way will be accessible from Barrie Road during this time.
  • This work is weather permitting. Paving will be rescheduled to Mon. 6/16 if it rains on Fri. 6/13.
  • A map visualizing this traffic update can be found here.


W. 65th Street

  • Sign installation, saw and seal of the roadway, and pavement striping is scheduled for the week of 6/16.


Barrie Road and Heritage Drive

  • Permanent pavement striping is scheduled for the week of 6/16