Construction Update - 8/23/24

Traffic Update

  • Expect short term delays driving on Barrie Road between W 65th Street and Heritage Drive during the week of 8/26. These delays may include hourly closures to install new storm sewer. Please plan your trips to account for these short-term delays.
  • Delays on Barrie Road can be up to 15 minutes. If that is too long of a delay, please refer to map for parking options.
  • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
  • A map visualizing this traffic update can be found here.

Barrie Road

  • Storm sewer installation will continue into the week of 8/26.
  • Roadway excavation is scheduled for the week of 8/26 following storm sewer installation. This work will cause traffic delays of up to 15 minutes on Barrie Road. A more detailed update will be sent out early next week prior to roadway excavation work.

Heritage Drive

  • Streetlight installation is complete.
  • Sidewalk installation is scheduled for the week of 8/26.
  • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


W. 65th Street

  • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
  • Xcel Energy’s relocation of their facilities is scheduled to begin late August or early September. Sorry for the delay.