Construction Update - 8/30/2024

Crews will not be working during the Monday, 9/2 Labor Day holiday.


Traffic Update

  • Access to Barrie Road from W 66th Street will be closed on Tuesday, 9/3 due to road excavation work and will likely open by 9/5.
  • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive during the week of 9/3. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
  • Access to Barrie Road businesses between W 66th Street and W 65th Street will be open from the north, with delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
  • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
  • A map visualizing this traffic update can be found here.

Barrie Road

  • Storm sewer installation is complete.
  • Roadway excavation is scheduled for the week of 9/3 starting on W 66thStreet.
    • This work will cause traffic delays of up to 30 minutes on Barrie Road. Updates will be sent out throughout next week as roadway excavation continues north from W. 66th Street to Heritage Drive.
    • Excavation work is anticipated to last at least one week.


Heritage Drive

  • Sidewalk installation is complete.
  • Irrigation repairs and retaining wall installation is scheduled for the week of 9/9.
  • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


W. 65th Street

  • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
  • Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.