Construction Update - 8/9/2024

Traffic Update

  • Intersection of Barrie Road & Heritage Drive will be closed periodically for storm sewer installation.
  • Expect short term delays driving on Barrie Road between W 65th Street and Heritage Drive during the week of 8/12. These delays may include hourly closures to install new storm sewer. Please plan your trips to account for these short-term delays.
  • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
  • A map visualizing this traffic update can be found here.


Barrie Road

  • Water infrastructure improvements are complete.
  • Storm sewer installation will continue into the week of 8/12.


Heritage Drive

  • Sidewalk installation is scheduled for the week of 8/19.
  • Streetlight installation is scheduled for the week of 8/12.
  • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


W. 65th Street

  • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
  • Xcel Energy’s relocation of their facilities has been delayed. Sorry for the delay.