Construction Update - 8/9/2024
Traffic Update
- Intersection of Barrie Road & Heritage Drive will be closed periodically for storm sewer installation.
- Expect short term delays driving on Barrie Road between W 65th Street and Heritage Drive during the week of 8/12. These delays may include hourly closures to install new storm sewer. Please plan your trips to account for these short-term delays.
- Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
- A map visualizing this traffic update can be found here.
Barrie Road
- Water infrastructure improvements are complete.
- Storm sewer installation will continue into the week of 8/12.
Heritage Drive
- Sidewalk installation is scheduled for the week of 8/19.
- Streetlight installation is scheduled for the week of 8/12.
- Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.
W. 65th Street
- While the street is gravel, it is open to vehicular traffic. Please drive slowly.
- Xcel Energy’s relocation of their facilities has been delayed. Sorry for the delay.