Construction Update - 9/13/2024
Construction Update – 9/13/2024
Traffic Update
- Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive during the week of 9/16 due to curb installation. Please plan your trips to account for these short-term delays.
- Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
- A map visualizing this traffic update can be found here.
Barrie Road
- Roadway excavation is complete.
- Curb installation is scheduled for late during the week of 9/16.
Heritage Drive
- Irrigation repairs will continue into week of 9/16.
- Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.
W. 65th Street
- While the street is gravel, it is open to vehicular traffic. Please drive slowly.
- Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.
Share Construction Update - 9/13/2024 on Facebook
Share Construction Update - 9/13/2024 on Twitter
Share Construction Update - 9/13/2024 on Linkedin
Email Construction Update - 9/13/2024 link