Construction Update - 9/13/2024

Construction Update – 9/13/2024


Traffic Update

  • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive during the week of 9/16 due to curb installation. Please plan your trips to account for these short-term delays.
  • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
  • A map visualizing this traffic update can be found here.


Barrie Road

  • Roadway excavation is complete.
  • Curb installation is scheduled for late during the week of 9/16.


Heritage Drive

  • Irrigation repairs will continue into week of 9/16.
  • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


W. 65th Street

  • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
  • Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.


Share Construction Update - 9/13/2024 on Facebook Share Construction Update - 9/13/2024 on Twitter Share Construction Update - 9/13/2024 on Linkedin Email Construction Update - 9/13/2024 link
#<Object:0x0000000049bdbbb0>