Barrie Road
- Driveway aprons and concrete sidewalk installation is scheduled to begin the week of 9/23 and conclude the week of 9/30.
Heritage Drive
- Irrigation repairs will continue into week of 9/23.
- Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.
W. 65th Street
- Xcel Energy’s relocation of their facilities is scheduled to continue into the week of 9/23.
- While the street is gravel, it is open to vehicular traffic. Please drive slowly.