Vernon Avenue & Highway 100 Interchange Project

Share Vernon Avenue & Highway 100 Interchange Project on Facebook Share Vernon Avenue & Highway 100 Interchange Project on Twitter Share Vernon Avenue & Highway 100 Interchange Project on Linkedin Email Vernon Avenue & Highway 100 Interchange Project link

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings
  • January 26, 2026 Update: Northbound Onramp

    Share January 26, 2026 Update: Northbound Onramp on Facebook Share January 26, 2026 Update: Northbound Onramp on Twitter Share January 26, 2026 Update: Northbound Onramp on Linkedin Email January 26, 2026 Update: Northbound Onramp link

    Northbound Ramp Closure Update: The noise wall planking has been delivered. With the cold weather forecast, the contractor has again delayed starting installation. Work will start on Monday, February 2. This is different than the reported January 21 and January 26 dates. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue. Thanks

  • January 20, 2026 Update

    Share January 20, 2026 Update on Facebook Share January 20, 2026 Update on Twitter Share January 20, 2026 Update on Linkedin Email January 20, 2026 Update link

    Due to the forecasted, extreme cold weather, the contractor has decided to push the start date of the short term northbound Highway 100 on-ramp closures for noise wall plank installation to Monday, January 26. Thanks for the understanding.

  • January 13, 2026 Update

    Share January 13, 2026 Update on Facebook Share January 13, 2026 Update on Twitter Share January 13, 2026 Update on Linkedin Email January 13, 2026 Update link

    The noise wall planking is scheduled for delivery late this week and early next week. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. Work will start on January 21. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue.

  • December 11, 2025 Update

    Share December 11, 2025 Update on Facebook Share December 11, 2025 Update on Twitter Share December 11, 2025 Update on Linkedin Email December 11, 2025 Update link
    supporting image

    Great News, the intersection of Interlachen Blvd, Vernon Ave and Gus Young Lane reopened to traffic on this week with the use of temporary signals. The temporary signals will be operating until the contractor resumes work in the spring. The exact date will be determined based on weather. The traffic signals and power to light the signals on the Highway 100 Bridge are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share. There may be a couple northbound Highway 100 onramp closures next week to straighten noise wall posts. There is not enough room for the contractor to complete this work with the ramp open. It would be a temporary closure between 10 am – 2 pm over two days. Access to northbound Highway 100 would be from Benton Avenue for those durations. Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.

  • December 3, 2025 Update

    Share December 3, 2025 Update on Facebook Share December 3, 2025 Update on Twitter Share December 3, 2025 Update on Linkedin Email December 3, 2025 Update link

    The contractor will work on the Vernon Avenue Bridge until December 12. The last concrete pour will occur this week. Concrete forms will be removed next week and the site cleaned up. Major construction operations will stop for the winter. Gus Young Lane will be reopened to traffic on December 10, 2025 with the use of temporary signals. The temporary signals will be operating until the contractor resumes work in the spring. The exact date will be determined based on weather. The traffic signals and power to light the signals on the Highway 100 Bridge are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share.

    Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.

  • November 26, 2025 Update

    Share November 26, 2025 Update on Facebook Share November 26, 2025 Update on Twitter Share November 26, 2025 Update on Linkedin Email November 26, 2025 Update link

    Since November 15, the on and off-ramps of Highway 100 and the Highway 100 bridge have been open to traffic. Traffic is currently controlled by stop signs. The traffic signals and power to light the signals are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share.

    As previously detailed, the contractor will work as long as weather allows on the Vernon Ave Bridge over the railway this fall. It looks like by mid-December, work will stop. The contractor is trying to get far enough along to be able to place the bridge beams this winter so work can resume in the spring when weather allows. We still plan to open Gus Young Lane to Interlachen Blvd and Vernon Ave with a temporary traffic signal. The contractor will store some materials and equipment at 5146 Eden Avenue during the pause in construction. Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.

  • November 13, 2025 Update

    Share November 13, 2025 Update on Facebook Share November 13, 2025 Update on Twitter Share November 13, 2025 Update on Linkedin Email November 13, 2025 Update link
    supporting image

    Overnight on Friday, November 14, into Saturday, November 15, the on and off-ramps of Highway 100 and the Highway 100 bridge will be re-opened to traffic. This includes all the on and off-ramps. There has been a delay in the noise wall planking. Space is very tight along the on-ramp to northbound Highway 100 to be able to install the planking under traffic. The contractor is developing options on how to install those planks where space is tight. More information will be provided when known.

    As previously detailed, the contractor will work as long as weather allows on the Vernon Ave Bridge over the railway this fall. Work will resume in the spring when weather allows. When work stops this winter, we will open Gus Young Lane to Interlachen Blvd and Vernon Ave with a temporary traffic signal. The contractor will store some materials and equipment at 5146 Eden Avenue during the pause in construction. This week was our last virtual meeting. Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.

  • November 6, 2025 Update

    Share November 6, 2025 Update on Facebook Share November 6, 2025 Update on Twitter Share November 6, 2025 Update on Linkedin Email November 6, 2025 Update link

    Overnight on Friday, November 14, into Saturday, November 15, the off-ramps of Highway 100 will be re-opened to traffic. This includes northbound Highway 100 existing to 50th Street. Vehicles will be able to go left towards the Grandview District or right towards 50th and France District. It also includes southbound Highway 100 exiting across Vernon Avenue, behind Hilltop Restaurant to Arcadia Avenue.

    The northbound on-ramp to Highway 100 is still under discussion. There has been a delay in the noise wall planking. Space is very tight along the on-ramp to install the planking safely under traffic. We are reviewing options to get that on-ramp open.

    As previously detailed, the contractor will work as long as weather allows on the Vernon Ave Bridge over the railway this fall. Work will resume in the spring when weather allows, tentatively April. When work stops this winter, we will open Gus Young Lane to Interlachen Blvd and Vernon Ave with a temporary traffic signal.

    Thank you for your patience.

  • October 30, 2025 Update

    Share October 30, 2025 Update on Facebook Share October 30, 2025 Update on Twitter Share October 30, 2025 Update on Linkedin Email October 30, 2025 Update link
    supporting image

    Progress continues towards re-opening the Highway 100 Bridge and related ramps to Highway 100 by mid-November. As previously detailed, the contractor will work as long as weather allows on the Vernon Ave Bridge over the railway this fall. Work will resume in the spring when weather allows, tentatively April. When work stops, we will open Gus Young Lane to Interlachen Blvd and Vernon Ave with a temporary traffic signal.

    Next week will see a continuation of work such as the final layer of paving, noise wall planking, sidewalk railings, light poles, and site clean-up. It should be noted that the project team found locations for 13 new trees within medians on both 50th Street and Vernon Ave. Thank you for your patience.

  • October 24, 2025 Update

    Share October 24, 2025 Update on Facebook Share October 24, 2025 Update on Twitter Share October 24, 2025 Update on Linkedin Email October 24, 2025 Update link
    supporting image

    Concrete work on the west abutment started today. Photo attached. Thanks

Page last updated: 26 Jan 2026, 03:02 PM