Vernon Avenue & Highway 100 Interchange Project

Share Vernon Avenue & Highway 100 Interchange Project on Facebook Share Vernon Avenue & Highway 100 Interchange Project on Twitter Share Vernon Avenue & Highway 100 Interchange Project on Linkedin Email Vernon Avenue & Highway 100 Interchange Project link

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings
  • July 15, 2025 Update

    Share July 15, 2025 Update on Facebook Share July 15, 2025 Update on Twitter Share July 15, 2025 Update on Linkedin Email July 15, 2025 Update link
    supporting image

    UPDATED RAMP CLOSURE DATE: The date for the closure of northbound Highway 100 on-ramp from 50th Street has changed to July 28 until late fall. With a closure of the northbound Highway 100 on-ramp will come construction of the noise wall. One detour will be southbound Highway 100 from Eden Avenue to eastbound Highway 62 to northbound Highway 100. The local detour will utilize the frontage roads and the northbound Highway 100 on-ramp at Benton Avenue. Maps are available on this site.

    Thanks for your patience as the project continues.

  • July 11, 2025 Update

    Share July 11, 2025 Update on Facebook Share July 11, 2025 Update on Twitter Share July 11, 2025 Update on Linkedin Email July 11, 2025 Update link
    supporting image

    Remember businesses are open and accessible. Please be patient when walking, biking, or driving in the area.

    Underground utility work continues in the intersection of Interlachen Blvd and Vernon Avenue. The intersection will be open to traffic, but traffic will be shifted to the south side next week. Be patient in this intersection. The Edina Grandview Liquor store will open Monday / Tuesday next week with new sidewalks and concrete entrance.

    The northbound Highway 100 on-ramp is scheduled to close on July 21 until late fall. With a closure of the northbound Highway 100 on-ramp will come construction of the noise wall. One detour will be southbound Highway 100 from Eden Avenue to eastbound Highway 62 to northbound Highway 100. The local detour will utilize the frontage roads and the northbound Highway 100 on-ramp at Benton Avenue. Maps are available on this site.

    Thanks for your patience as the project continues.

  • July 3, 2025 Update

    Share July 3, 2025 Update on Facebook Share July 3, 2025 Update on Twitter Share July 3, 2025 Update on Linkedin Email July 3, 2025 Update link
    supporting image

    Remember businesses are open and accessible. Please be patient when walking, biking, or driving in the area. With construction comes noise, dust, traffic congestion and other construction related issues.

    Underground utility work continues in the intersection of Interlachen Blvd and Vernon Avenue. The intersection will be open to traffic, but traffic will be shifted and adjusted back and forth based on the working area. Be patient in this intersection. The Edina Grandview Liquor store will soon have new sidewalks and concrete entrance. The store is scheduled to re-open July 14.

    Discussions about closing Highway 100 on and off ramps for construction have started. The east side and west side may have different schedules. The tentative plan is to close northbound Highway 100 on-ramp on July 21 until late fall. With a closure of the northbound Highway 100 on-ramp will come construction of the noise wall. One detour will be southbound Highway 100 from Eden Avenue to eastbound Highway 62 to northbound Highway 100. The local detour will utilize the frontage roads and the northbound Highway 100 on-ramp at Benton Avenue. More information and maps coming soon when this work is confirmed.

    Thanks for your patience as the project continues.

  • June 26, 2025 Update

    Share June 26, 2025 Update on Facebook Share June 26, 2025 Update on Twitter Share June 26, 2025 Update on Linkedin Email June 26, 2025 Update link
    supporting image

    Remember businesses are open and accessible. Please be patient when walking, biking, or driving in the area. There are no changes planned to traffic management in the short term. With construction comes noise, dust, traffic congestion and other construction related issues. Thanks for your patience as the project continues.

    Underground utility work will be occurring in the intersection of Interlachen Blvd and Vernon Avenue. The intersection will be open to traffic, but traffic will be shifted and adjusted back and forth based on the working area. Be patient in this intersection. The Edina Grandview Liquor store will soon have new sidewalks and concrete entrance. Starting Monday, June 30, the contractor will begin removals in preparation for new concrete.

    An Xcel Energy power line is in a different location than expected within the CPKC Railroad right-of-way. The power line needs to be relocated before the foundation for the west side of the Vernon Avenue Bridge can be built. The current agreements between the parties are outdated and neither party will work until the necessary agreements and permits are secured. If this is not completed in the next few weeks, it could have major impacts to the project schedule.

    Discussions about closing Highway 100 on and off ramps for construction have started. The east side and west side may have different schedules. The contractor is developing a plan now for consideration. One or more ramps could close as soon as mid-July. With a closure of the northbound Highway 100 on-ramp will come construction of the noise wall.

  • June 12, 2025 Update

    Share June 12, 2025 Update on Facebook Share June 12, 2025 Update on Twitter Share June 12, 2025 Update on Linkedin Email June 12, 2025 Update link
    supporting image

    There are people walking and biking in the crosswalks. State law requires drivers to yield to those individuals. Safety is a priority for all involved. Please be patient. There are no changes planned to traffic management in the short term. There will be night work on Highway 100. Remember businesses are open and accessible. With construction comes noise, dust, traffic congestion and other construction related issues. Thanks for your patience as the project continues full speed ahead.

    The contractor continues piling driving steel supports for the new Highway 100 bridge this week. The piling on the west side of Highway 100 should be completed this week. The piling on the east side of Highway 100 should be completed by the end of next week. Steel piling was drilled into the ground adjacent to Davanni’s Pizza. These will provide space for the contractor to work and protect their property. Crushing / recycling old street pavement continues as you can see the material piles grow. Construction of the retaining walls along the north side of Vernon Ave adjacent to Hawthrone Court continues. The contractor has placed sensors and cooling equipment, linked to their computers, to track the temperature and curing of the concrete in the Highway 100 median. This will ensure it meets the project requirements.

  • June 5, 2025 Update

    Share June 5, 2025 Update on Facebook Share June 5, 2025 Update on Twitter Share June 5, 2025 Update on Linkedin Email June 5, 2025 Update link
    supporting image

    There are people walking and biking in the crosswalks. State law requires drivers to yield to those individuals. Safety is a priority for all involved. Please be patient. There are no changes planned to traffic management in the short term. There will be occasionally night work on Highway 100.

    Remember businesses are open and accessible. With construction comes noise, dust, traffic congestion and other construction related issues. Thanks for your patience as the project continues full speed ahead.

    The contractor continues piling driving steel supports for the new Highway 100 bridge this week. This work will be noisy and conducted during normal working hours. They also started crushing / recycling old street pavement to use on the project. Better to recycle onsite than to haul the material offsite and haul in new material. This will also be noisy. Retaining wall along the north side of Vernon Ave adjacent to Hawthrone Court are also being constructed.

  • May 29, 2025 Update

    Share May 29, 2025 Update on Facebook Share May 29, 2025 Update on Twitter Share May 29, 2025 Update on Linkedin Email May 29, 2025 Update link

    Remember businesses are open and accessible. With construction comes noise, dust, traffic congestion and other construction related issues. Thanks for your patience as the project continues full speed ahead.

    The contractor started piling driving steel supports for the new Highway 100 bridge this week. This work will be noisy and conducted during normal working hours. They also started crushing / recycling old street pavement to use on the project. Better to recycle onsite than to haul the material offsite and haul in new material. This will also be noisy.

    Traffic has increased along Eden Avenue due to the detour route. It does get congested. Please allow extra time to get to your appointments. Please note that during morning and afternoon school pick-up times, Eden Avenue gets very busy. Alternate routes may be another option during those peak times. Also be considerate of your fellow drivers trying to enter Eden Avenue but more importantly pedestrians. There are people walking and biking in the crosswalks. State law requires drivers to yield to those individuals. Safety is a priority for all involved. Please be patient.

    There have been some changes to traffic management on Highway 100 without the city knowing. We are working with our project partners to ensure the information we provide is accurate. The weekend closure detour route was adjusted from Excelsior Blvd to Highway 394. And short-term lane closures occurred Tuesday morning. A MnDOT functional group made the decision without consulting the project team. We are working with our MnDOT representatives to better understand what is occurring.

  • May 21, 2025 Update

    Share May 21, 2025 Update on Facebook Share May 21, 2025 Update on Twitter Share May 21, 2025 Update on Linkedin Email May 21, 2025 Update link

    Thanks for the continued patience. Remember businesses are open and accessible.

    On Tuesday, May 27, the contractor intends to start piling driving steel supports for the new Highway 100 bridge. This work will be loud and conducted during normal working hours. The remainder of this week will include excavation work for retaining walls and bridge supports. Next week installation of watermain, storm sewer, and sanitary sewer pipes will start.

    Eden Avenue Traffic: Traffic has increased along Eden Avenue due to the detour route. It does get congested. Please allow extra time to get to your appointments. Please note that during morning and afternoon school pick-up times, Eden Avenue gets very busy. Alternate routes may be another option during those peak times. Also be considerate of your fellow drivers trying to enter Eden Avenue but more importantly pedestrians. There are people walking and biking in the crosswalks. State law requires drivers to yield to those individuals. Safety is a priority for all involved. Please be patient.

    Thanks, Chad Millner, City Engineer.

  • May 20, 2025 Update

    Share May 20, 2025 Update on Facebook Share May 20, 2025 Update on Twitter Share May 20, 2025 Update on Linkedin Email May 20, 2025 Update link
    supporting image

    Highway 100 opened early Monday morning as scheduled. The bridge was successfully removed. Ames Construction continues with full speed construction operations. Thanks

  • May 14, 2025 Update

    Share May 14, 2025 Update on Facebook Share May 14, 2025 Update on Twitter Share May 14, 2025 Update on Linkedin Email May 14, 2025 Update link

    Thank you for your continued patience. Remember businesses are open and accessible. The project has another major milestone coming up.

    Highway 100 Bridge Update: The Highway 100 Bridge will be removed starting at 10 pm on Friday, May 16 until 5 am on Monday, May 19. The removal will occur over a weekend closure of Highway 100. Work will occur 24-hrs during that weekend closure. On May 16 (not May 14 as shown on the maps), the on-ramp to northbound Highway100 from Grange Rd will be closed and remain closed until further notice. This closure allows the contractor to prep for the full closure of Highway 100. The ramp is too close to the work area to allow for safe traffic operations and safe construction activities following removal of the bridge. Recall the on-ramp to northbound Highway 100 from 50th Street will still be open before and after bridge removal operations over the weekend closure. During the Highway 100 weekend closure starting at 9 pm on Friday, May 16 until 5 am on Monday, May 19, access to northbound Highway 100 from 50th Street will be closed. A detour to access northbound Highway 100 using France Avenue will be signed. The access to southbound Highway 100 will be maintained from Eden Avenue on the west side of Highway 100. The regional detour is Highway 62 to Highway 169 to Highway 394. Updated maps are being created now and will be posted at this site.

    Eden Avenue Traffic: Traffic has increased along Eden Avenue due to the detour route. It does get congested. Please allow extra time to get to your appointments. Please note that during morning and afternoon school pick-up times, Eden Avenue gets very busy. Alternate routes may be another option during those peak times. Also be considerate of your fellow drivers trying to enter Eden Avenue but more importantly pedestrians. There are people walking and biking in the crosswalks. State law requires drivers to yield to those individuals. Safety is a priority for all involved. Please be patient.

    Thanks, Chad Millner, City Engineer.

Page last updated: 15 Jul 2025, 11:31 AM