April 28 2026 Update

The contractor intends to pour the Vernon Avenue bridge deck on Thursday, April 30. There are lots of things left to do after that. They need the deck to cure for a specified amount of time. When the deck is ready, pour the sidewalk, median, and concrete barriers on the bridge. Finish utility work on the west side of the bridge. Install railings, lights, and pavement markings on the bridge. Install gravel base materials between the bridge and street, place bituminous, traffic signals, pedestrian ramps, sidewalks, lights, and other misc. items. Lots of items left to complete prior to the road opening by the end of June. Thanks for the patience.