August 26, 2025 Update

Beams will be lifted into place next week during the night. This will include night-time closures. Tuesday 9/2 and Wednesday 9/3 nights from 10pm to 5am, Northbound Highway 100 will be closed. Thursday 9/4 and Friday 9/5 nights from 10pm to 5am, Southbound Highway 100 will be closed. The regional detour is HWY 62 to HWY 169 to I-394, and vice versa.

Northbound exit to Grange Rd and Southbound Exit to Arcadia Ave will be closed beginning September 15th and anticipated to last until mid-November. The project team is working on developing maps and resources that will be posted to the site and emailed out soon.

The week of September 15th, the contractor is planning to begin crushing / recycling old street pavement to use on the project at the stockpile on the East side of 100. Better to recycle onsite than to haul the material offsite and haul in new material. This will also be noisy/dusty.

Please be patient in the area, especially with schools beginning this week. Remember that businesses are open and accessible. Thanks, Derek Huston

Share August 26, 2025 Update on Facebook Share August 26, 2025 Update on Twitter Share August 26, 2025 Update on Linkedin Email August 26, 2025 Update link
#<Object:0x000000001a5a9938>