December 3, 2025 Update
The contractor will work on the Vernon Avenue Bridge until December 12. The last concrete pour will occur this week. Concrete forms will be removed next week and the site cleaned up. Major construction operations will stop for the winter. Gus Young Lane will be reopened to traffic on December 10, 2025 with the use of temporary signals. The temporary signals will be operating until the contractor resumes work in the spring. The exact date will be determined based on weather. The traffic signals and power to light the signals on the Highway 100 Bridge are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share.
Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.