March 31, 2026 Update
Due to the weather forecast, the noise wall along the northbound Highway 100 onramp from 50th Street will continue to have sporadic daily closures between 9 am and 4 pm until April 10. The contractor is scheduled to place beams on the railroad bridge on April 7. This will require westbound 50th Street to be detoured to Eden Avenue except traffic using the northbound Highway 100 onramp. This will be a one day operation. Starting April 20, Gus Young Lane will be closed until late June to create enough space for construction access for underground utility, bridge, and street construction. Other than the Gus Young closure, traffic routing will remain approximately the same. Thanks, Chad Millner.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends