Progress continues towards re-opening the Highway 100 Bridge and related on- & off-ramps to Highway 100 by mid-November. The contractor has completed most of the concrete sidewalk, curb & gutter, and the first layers of asphalt paving. The final layer of paving is tentatively scheduled for the week of November 3. Noise wall planking is also expected to start November 3, 2025. The project team has recently reviewed adding trees within some of the medians. Sightlines and maintenance areas were reviewed. It was determined that 3 trees can be planted east of the Highway 100 on 50th Street. 10 trees can be planted west of Highway 100 on Vernon Avenue. There are 6 large boxed tress in the city hall parking lot that will be used for a portion of these plantings. We thank everyone for their patience during construction.