October 8, 2025 Update

Work started this week on the west abutment of the Vernon Avenue bridge. This is good news but there is not enough time to finish that portion of the project by mid-November. The project team is analyzing potential construction schedules and costs related to this work. As soon as a decision is made, we will communicate that. Much of the concrete curb and gutter on Vernon Avenue, 50th Street, and the new on- & off-ramps will be installed this week. The portion of the project around the Highway 100 Bridge including on- and off-ramps is on schedule to re-open by mid-November.