Project Update March 21, 2024
Staff and consultants continue to finish design the Vernon Ave and 50th Street at Highway 100 Interchange Project. Plans are 90% complete. We continue to get great feedback from our partner agencies, Hennepin County and MnDOT. Plans and specifications are scheduled to be complete in June 2024 with a bid opening in September 2024. We are anticipated the contractor could start work after November 15, 2024, close Vernon Ave and 50th Street to traffic in January 2025 and be required to re-open the streets to traffic by November 2025.