Construction Update 10/1 (current week, 10/6, 10/13)
Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
This week
- Grading for the new roadway is underway
- Placement of gravel for the new roadway base will also begin this week
Week of 10/6
- Placement of gravel for the new roadway base.
- Placement of new concrete curb and gutter.
- Preparation and pouring of new sidewalk and driveways.
Week of 10/13
- Paving of asphalt driveways and the first layer of the new roadway.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
Share Construction Update 10/1 (current week, 10/6, 10/13) on Facebook
Share Construction Update 10/1 (current week, 10/6, 10/13) on Twitter
Share Construction Update 10/1 (current week, 10/6, 10/13) on Linkedin
Email Construction Update 10/1 (current week, 10/6, 10/13) link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends