York Avenue Trunk Sanitary

The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.
Planned construction is for Summer/Fall 2025
The scope of construction includes;
- 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
- Phased closures of southbound York between the Promenade and 69th Street West
- New sections of road, curb, crosswalks and catch basins
The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.
Planned construction is for Summer/Fall 2025
The scope of construction includes;
- 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
- Phased closures of southbound York between the Promenade and 69th Street West
- New sections of road, curb, crosswalks and catch basins
-
Construction Update 9/9 (Current week, 9/15, and 9/22)
Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Facebook Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Twitter Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Linkedin Email Construction Update 9/9 (Current week, 9/15, and 9/22) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Traffic control change to Phase 2b, which closes eastbound 69th at the east most Galleria entrance is schedule for Wednesday September 17th.
This week
- Installation of new sanitary sewer pipe.
- Coordination with private utilities to locate, clear, deenergize or relocate lines on the alignment near 69th and York to prepare for late September sewer installation. This week there will be communications contractor working near 69th to do this work.
Week of 9/15
- Installation of new sanitary sewer pipe.
- A <1 day lane closure on northbound York right turn lane near 69th, likely the 16th or 17th of September.
- Traffic control change to Phase 2b, which closes eastbound 69th at the east most Galleria entrance
Week of 9/22
- Installation of new sanitary sewer pipe.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Construction Update 9/3 (Current week, 9/8, and 9/15)
Share Construction Update 9/3 (Current week, 9/8, and 9/15) on Facebook Share Construction Update 9/3 (Current week, 9/8, and 9/15) on Twitter Share Construction Update 9/3 (Current week, 9/8, and 9/15) on Linkedin Email Construction Update 9/3 (Current week, 9/8, and 9/15) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Signal electrical work at Hazelton.
- A 'quiet' week as we move forward in the second phase. The work in late September gets much more technical with many utility crossing near 69th, and relocation of part of the signal arms
This week
- Removal of bituminous pavement, curb and gutter, and sidewalk
- Installation of new gate valves. At this time, a shutdown of the existing water main is not expected for the work to occur
- Begin installation of new sanitary sewer pipe north of Hazelton Road
- Coordination with private utilities to locate, clear, deenergize or relocate lines on the alignment near 69th and York to prepare for late September sewer installation.
Week of 9/8
- Installation of new sanitary sewer pipe.
Week of 9/15
- Installation of new sanitary sewer pipe.
- A <1 day lane closure on northbound York right turn lane near 69th.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Phase 2 Traffic Signal troubleshooting - 8/28 special update
Share Phase 2 Traffic Signal troubleshooting - 8/28 special update on Facebook Share Phase 2 Traffic Signal troubleshooting - 8/28 special update on Twitter Share Phase 2 Traffic Signal troubleshooting - 8/28 special update on Linkedin Email Phase 2 Traffic Signal troubleshooting - 8/28 special update linkThe contractor and project staff are actively working with Hennepin County Traffic management staff to make the signals work better with the phase closures.
-
Construction Update 8/26 (Current week, 9/1 and 9/8)
Share Construction Update 8/26 (Current week, 9/1 and 9/8) on Facebook Share Construction Update 8/26 (Current week, 9/1 and 9/8) on Twitter Share Construction Update 8/26 (Current week, 9/1 and 9/8) on Linkedin Email Construction Update 8/26 (Current week, 9/1 and 9/8) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- The switch over for Phase 2 will occur tomorrow, Wednesday, August 27 around 6-7am. With this change, southbound York Ave will be closed to traffic from 69th Street to just north of Hazelton Road. The current detour to France Ave will remain unchanged.
- The phase change will come with 1 day of closure for both Hazelton Road and 70th Street (2 eastbound intersection lanes, right and through at York). Hazelton Road is expected to re-open to traffic about 6pm on Wednesday August 27.
This week
- Installation of pavement markings
- Changeover of southbound York Ave closure from phase 1 to phase 2
- Installation of erosion control measures within phase 2 work area
- Removal of bituminous pavement within phase 2 work area
Week of 9/1
- Removal of bituminous pavement, curb and gutter, and sidewalk
- Installation of new gate valves. At this time, a shutdown of the existing water main is not expected for the work to occur
- Begin installation of new sanitary sewer pipe north of Hazelton Road
Week of 9/8
- Installation of new sanitary sewer pipe.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Construction Update 8/19 (Current week, 8/25 and 9/1)
Share Construction Update 8/19 (Current week, 8/25 and 9/1) on Facebook Share Construction Update 8/19 (Current week, 8/25 and 9/1) on Twitter Share Construction Update 8/19 (Current week, 8/25 and 9/1) on Linkedin Email Construction Update 8/19 (Current week, 8/25 and 9/1) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with turf restoration, the paving of the final layer of bituminous pavement, and pavement markings/signs.
- The switch over for Phase 2 is now expected to occur on Wednesday, August 27. With this change, southbound York Ave will be closed to traffic from just 69th Street to just north of Hazelton Road. The current detour to France Ave will remain unchanged.
- The phase change will come with 1 day of closure for both Hazelton Road and 70th Street (2 eastbound intersection lanes, right and through at York), also expected to occur on August 27. Hazelton Road is expected to re-open to traffic on Thursday, August 28.
This week
- Placement of topsoil and sod
- Paving of final layer of bituminous pavement on Thursday, August 21. There may be short durations (less than 15 minutes) while pavement is being placed in or in front of driveways where access is not possible. Please be patient.
Week of 8/25
- Placement of sod
- Installation of traffic signs and pavement markings
- Changeover of southbound York Ave closure from phase 1 to phase 2
- Installation of erosion control measures within phase 2 work area
- Removal of bituminous pavement within phase 2 work area
Week of 9/1
- Removal of bituminous pavement, curb and gutter, and sidewalk
- Installation of new gate valves. At this time, a shutdown of the existing water main is not expected for the work to occur
- Begin installation of new sanitary sewer pipe north of Hazelton Road
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Construction Update 8/12 (Current week, 8/18 and 8/25)
Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Facebook Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Twitter Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Linkedin Email Construction Update 8/12 (Current week, 8/18 and 8/25) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with restoration of roadways. This phase will be paved, striped and open to traffic before we move to Phase 2, north of Hazelton.
- Most probable time for Phase 2 switch over would be September 2, after the holiday weekend.
- The phase change could come with 1 day of closure for Both Hazelton Road and 70th Street (2 eastbound intersection lanes, right and through at York)
This week
- Paving of first two layers of bituminous pavement (roadway and driveways). There may be short durations (less than 15 minutes) while pavement is being placed in or in front of driveways where access is not possible. Please be patient.
- Placement of remaining concrete sidewalk
- A contractor for Xcel Energy may be on site to replace street lights this week. (Currently at-risk as Xcel is nonresponsive) If they miss this window, they may have to close a lane to work on the P1 area.
Week of 8/18
- Concrete cure time
- Installation of signs and pedestrian crossing equipment.
- Placement of topsoil
- The final layer of bituminous pavement may be paved this week (slight chance late week)
Week of 8/25
- The final layer of bituminous pavement will be paved this week
- Pavement markings
- Preparation for phase switch over.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Construction Update 8/5 (Current week, 8/11 and 8/18)
Share Construction Update 8/5 (Current week, 8/11 and 8/18) on Facebook Share Construction Update 8/5 (Current week, 8/11 and 8/18) on Twitter Share Construction Update 8/5 (Current week, 8/11 and 8/18) on Linkedin Email Construction Update 8/5 (Current week, 8/11 and 8/18) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with restoration of roadways. This phase will be paved, striped and open to traffic before we move to Phase 2, north of Hazelton.
This Week
- Placement of curb and gutter and concrete driveways is wrapping up this week
- Aggregate base finishing touches
Week of 8/11
- Paving of first two layers of bituminous pavement (roadway and driveways). There may be short durations (less than 15 minutes) while pavement is being placed in or in front of driveways where access is not possible. Please be patient.
- Placement of remaining concrete sidewalk
- A contractor for Xcel Energy may be on site to replace street lights this week.
Week of 8/18
- Concrete cure time
- Installation of signs
- Placement of topsoil
- The final layer of bituminous pavement may be paved this week
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Where'd the workers go? - Saturday work planned.
Share Where'd the workers go? - Saturday work planned. on Facebook Share Where'd the workers go? - Saturday work planned. on Twitter Share Where'd the workers go? - Saturday work planned. on Linkedin Email Where'd the workers go? - Saturday work planned. linkA quick Thursday update on the project schedule for the end of the week of 7/28:
We're expecting to see the concrete subcontractor on site later today, Friday and Saturday. Rain delayed their work on a separate project and there we delayed showing up to York.
We know it's frustrating to see waits during the project, but we do not expect delays to this phase. We'll let you know if conditions change or if do expect a delay. The remainder of this phase will have two more periods of low-to-no work, once for concrete cure time, and the next for blacktop time limitation between paving two layers and striping the road.
Thanks for your continued patience as the work progresses!
-Ross, William and Aaron,
-
Construction Update 7/29 (Current week, 8/4 and 8/11)
Share Construction Update 7/29 (Current week, 8/4 and 8/11) on Facebook Share Construction Update 7/29 (Current week, 8/4 and 8/11) on Twitter Share Construction Update 7/29 (Current week, 8/4 and 8/11) on Linkedin Email Construction Update 7/29 (Current week, 8/4 and 8/11) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with restoration of roadways. This phase will be paved, stripped and open to traffic before we move to Phase 2, north of Hazelton.
This Week
- Placement of curb and gutter, concrete driveways, walks, and final grade of aggregate base.
- A contractor for Xcel Energy may be on site to replace street lights this week or next.
Week of 8/4
- Aggregate base finishing touches, bituminous paving
- Additional concrete work
- A contractor for Xcel Energy may be on site to replace street lights this week.
Week of 8/11
- Concrete cure time
- Driveway paving this week or next
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
-
Construction Update 7/22 (current week, 7/28 and 8/24)
Share Construction Update 7/22 (current week, 7/28 and 8/24) on Facebook Share Construction Update 7/22 (current week, 7/28 and 8/24) on Twitter Share Construction Update 7/22 (current week, 7/28 and 8/24) on Linkedin Email Construction Update 7/22 (current week, 7/28 and 8/24) linkThanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with restoration of roadways. This phase will be paved, stripped and open to traffic before we move to Phase 2, north of Hazelton. We are working with the businesses north of Hazelton to introduce the Phase 2 traffic control plan so each can work with customers and suppliers for a smooth transition to phase 2 currently planned for the first week of September.
This week
- Placement of new road aggregate base in south phase.
- Michaels is on site doing work for Centerpointe Energy to replace private gas services.
Week of 7/28
- Placement of curb and gutter, concrete driveways, walks, and final grade of aggregate base.
- A contractor for Xcel Energy may be on site to replace street lights this week or next.
Week of 8/4
- Aggregate base finishing touches, bituminous paving
- placement of topsoil
- Additional concrete work
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
Who's Listening
-
Phone 952-903-5713 Email RBintner@EdinaMN.gov -
Phone 952-912-2629 Email wbauer@sehinc.com -
Phone 612-251-6956 Email jharrington@sehinc.com
Documents
FAQs
- What is the purpose of the York Avenue Trunk Sanitary Sewer Project?
- What work is included in the project, and will the area look any different when it’s finished?
- When is construction happening?
- How will traffic be affected during the project?
- Are there any anticipated service disruptions during construction?
- How much does the project cost and how is it funded?
- How can I stay informed about the project?
- Who can I contact with questions?