Construction Update 10/14 (current week, 10/20, 10/27)
Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- SEPARATE PROJECT IS CLOSING NORTHBOUND YORK FOR UP TO 2 WEEKS - October 15 - 31
- Northbound York Avenue (County Road 31) is closed between Hazelton Road and 70th Street. Crews will connect sanitary sewer and water lines for the future Southdale Library. Follow the posted detour. For more information, visit the Southdale Library construction page(External link). https://beheardhennepin.org/southdale-library(External link)
 
 - Southbound York Avenue is on schedule to re-open to traffic around the end of October.
 
This week
- Paving of asphalt driveways and the first two layers of the new roadway.
 - Placement of topsoil and preparation for seed/sod
 
Week of 10/20
- Seeding and placement of new sod
 - Preparation for and paving of final layer of new roadway
 - Signal and push button reestablishment
 
Week of 10/27
- Installation of traffic signs and pavement markings
 - Final clean-up
 
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
Share Construction Update 10/14 (current week, 10/20, 10/27) on Facebook
Share Construction Update 10/14 (current week, 10/20, 10/27) on Twitter
Share Construction Update 10/14 (current week, 10/20, 10/27) on Linkedin
Email Construction Update 10/14 (current week, 10/20, 10/27) link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends