Construction Update 10/21 (Current Week & 10/27)
Key Update
- Next Week: We project the probable reopening of southbound York Avenue on Thursday 10/30, or Friday 10/31.
This week
- Seeding and placement of new sod
- Preparation for and paving of final layer of new roadway
- Signal and push button reestablishment
Week of 10/27
- Installation of traffic signs and pavement markings
- Final clean-up
- The probable reopening of the southbound lane Thursday or Friday
- As always - weather dependent!
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina