Construction Update 6/10 (Current week, 6/16 and 6/23)

Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.

Key update:

  • Watermain and valve work on the evening of 6/10 at Hazelton and York will include night work and water service disruption to 3 block area of York Avenue. Water outage is expected to start at 9pm with the outage lasting until about 2am. Utility staff are notifying property managers to help get the word out to residents and report that Edina fire will be on fire watch during the outage.

This week

  • Traffic control set up went well and staff and Hennepin County monitored peak hours for possible adjustments. Please be cognizant of road closures and follow the signed detour. Do not attempt to drive past road closure barricades
  • Mobilization of equipment and materials on site with semi trucks and trailers
  • Milling and reclamation of the blacktop surface with a milling machine starts Wednesday. This work is noisy and can include some dust.
  • Hauling and stockpiling of reclaimed material within the construction zone
  • Temporary blacktop driveway exit for York Plaza area will be installed Friday.
  • Intermittent, but short-term (less than 10 minute) disruption to driveways expected during milling and reclamation operations.

Week of 6/16

  • Beginning of utility work with excavation, chance for additional emergency water outages as we work with old valves and insert new valves. Any outages required will immediately be communicated as they become known.
  • Utility work continues through the week. Excavation will be backfilled or fenced at the end of each day.
  • Please note any after-hours pedestrian access to the work zone to the City of Edina Police non-emergency line; at 952-826-1600

Week of 6/23

  • Utility work, installation of main sanitary sewer line by digging with a large excavator.

Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina.

Share Construction Update 6/10 (Current week, 6/16 and 6/23) on Facebook Share Construction Update 6/10 (Current week, 6/16 and 6/23) on Twitter Share Construction Update 6/10 (Current week, 6/16 and 6/23) on Linkedin Email Construction Update 6/10 (Current week, 6/16 and 6/23) link